Construction of Flood Mitigation Structure24GK0013

Construction of Flood Control Structure of Malogo River, Abutment ''A'' EB. Magalona, Negros Occidental

Construction of Flood Control Structure of Malogo River, Abutment ''A'' EB. Magalona, Negros Occidental is a DPWH-tracked public work in ENRIQUE B. MAGALONA (SARAVIA) (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱96,499,993.42. Status: Reported complete (DPWH). Contractor on record: SILVERGRACES CONST AND CONST SUPPLY. Figures trace to sumbong.

ENRIQUE B. MAGALONA (SARAVIA) (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Minulu - an River, Talisay City, Negros Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007641

₱2,046,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0005549

₱263,627.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0001414

₱218,533.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007643

₱189,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

408 projects · ₱4.0B total · 4 flags

4. Implementation

Contract Amount

₱96,499,993.42

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

January 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.