Construction of Flood Mitigation Structure24GK0010

Construction of Flood Control Structure of Imbang River (Upstream), Silay City, Negros Occidental

Construction of Flood Control Structure of Imbang River (Upstream), Silay City, Negros Occidental is a DPWH-tracked public work in SILAY CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱96,499,999.99. Status: Reported complete (DPWH). Contractor on record: SILVERGRACES CONST AND CONST SUPPLY. Figures trace to sumbong.

SILAY CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱28,789,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Matagoy Creek, Silay City, Negros Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007641

₱2,046,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0005549

₱263,627.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0001414

₱218,533.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007643

₱189,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,999.99

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

March 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.