Construction of Flood Mitigation Structure23HO0079

Construction of Bank Protection Structures along Brgy. Tupas - Brgy. Butong (Right Side Downstream), Ronda, Cebu

Construction of Bank Protection Structures along Brgy. Tupas - Brgy. Butong (Right Side Downstream), Ronda, Cebu is a DPWH-tracked public work in RONDA (CEBU), CEBU, Region VII. Reported contract value: ₱72,372,872.60. Status: Reported complete (DPWH). Contractor on record: JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY. Figures trace to sumbong.

RONDA (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Wall Structures at Sitio Aransana - Sitio Sulok (Right Side Upstream), Brgy. Mindanao, Malabuyoc, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 7th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,372,872.60

Progress

Reported complete (DPWH)

Start Date

March 16, 2023

Target End

December 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.