Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: Cebu 7th District Engineering Office awarded 164 of 170 recorded flood-control contracts (96.5%) at 99.5% or more of their Approved Budget for the Contract, versus 70.4% for flood-control contracts nationwide (26.1 percentage points higher; binomial p = 2.3e-18), across 30 contractors. Source: DPWH / Sumbong sa Pangulo contract records; each contract is listed below. This pattern may result from consistently competitive bidding or careful cost estimation.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Cebu 7th District Engineering Office: contracts
164 of 170 contracts (96.5%) at ≥99.5% of ABC · peer baseline 70.4% · gap +26.1 pts · binomial p = 2.3e-18. Source: DPWH transparency portal and Sumbong sa Pangulo records (linked per contract).
| Contract | Title | Contractor | % of ABC | Source |
|---|---|---|---|---|
| 22HO0049 | Improvement of Riverbank along Polo River, Sta. 0 + 000 - Sta. 0 + 700, Alcantara, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0074 | Construction of Seawall Protection Works along Santander - Balili - Toledo Road, Brgy. Sto Niño, Sta. 0 + 000 - Sta. 0 + 167.00, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0048 | Improvement of Riverbank along Parale River, Sta. 0 + 000 - Sta. 0 + 700, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0068 | Construction of seawall protection along Santander - Barili-Toledo Road at Brgy. Poblacion to Brgy. Legaspi, Sta. 0+000 - Sta. 0+167, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0065 | Construction of Road Dike along Valencia River (Right Side), Alegria, Cebu | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 22HO0067 | Construction of Road Dike along Pawa River, Damanjug, Cebu | WORLDWIDE BUILDERS / QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 22HO0005 | Construction of Tapon-Tangil Seawall, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0086 | Construction of Seawall Protection Works along Santander-Barili-Toledo Road at Brgy. Legaspi to Brgy. Poblacion, Sta. 0 + 000 - Sta. 0 + 167, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0003 | Construction of Ginatilan Flood Control (Upstream), Ginatilan, Cebu | FIRST GRANDEUR BUILDERS | 100.00% | DPWH |
| 22HO0078 | Construction of Seawall Protection Works along Santander-Barili-Toledo Road, Barangay Madridejos, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0077 | Construction of Seawall Protection Works along Santander-Barili-Toledo Rd at Brgy. Felomina, Sta. 0 + 000 - Sta. 0 + 167.00, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0076 | Construction of Revetment Wall along Brgy. Talaba River Flood Control, Ronda, Cebu | QM BUILDERS / FIRST GRANDEUR BUILDERS | 100.00% | DPWH |
| 22HO0075 | Construction of Seawall Protection Works along Santander - Balili - Toledo Road, Brgy. Poblacion II, Sta. 0 + 000 - Sta. 0 + 167.00, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0060 | Construction of Waterway along Manlapay River (Section 1), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0059 | Construction of Tapon-Tangil Seawall (L/S), Sta. 0 + 000 - Sta. 0 + 181, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0080 | Construction of of Seawall Protection Works along Santander-Barili-Toledo Rd at Brgy. Poblacion, Sta. 0 + 000 - Sta. 0 + 167.00, Moalboal, Cebu | RCDG CONST CORP | 100.00% | DPWH |
| 22HO0069 | Construction of Waterway along Tubod River (Section 1), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0004 | Construction of Poblacion Ronda Seawall, Ronda, Cebu | WORLDWIDE BUILDERS / QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 22HO0061 | Construction of Waterway along Manlapay River (Section 2), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0087 | Construction of Seawall Protection Works along Santander-Barili-Toledo Road at Brgy. Legaspi, Sta. 0 + 000 - Sta. 0 + 167, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0066 | Construction of Road Dike along Kang-actol River, Damanjug, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 22HO0057 | Construction of Revetment Wall along Polo River, Brgy. Polo, Sta. 0 + 000 - Sta. 0 + 143.00, Alcantara, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0056 | Construction of Slope Protection Structure along Basak Section, Badian, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0064 | Construction of Road Dike along Valencia River (Left Side), Alegria, Cebu | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 22HO0063 | Construction of Road Dike along Kabalaasnan River, Damanjug, Cebu | WORLDWIDE BUILDERS / QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 22HO0007 | Construction of Ylaya River Control, Ylaya, Ronda, Cebu | DT&C CONST | 100.00% | DPWH |
| 22HO0079 | Construction of Seawall Protection Works along Santander-Barili-Toledo Rd at Brgy. Felomina - Brgy. Madridejos, Sta. 0 + 000 - Sta. 0 + 167.00, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0039 | Construction of Alegria Seawall, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0050 | Improvement of Riverbank, Sta. 0 + 000 - Sta. 0 + 651, Madredijos, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0054 | Construction of Revetment Wall along Brgy. Vive River Flood Control (Section 2), Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 22HO0073 | Construction of of Seawall Protection Works along Santander-Barili-Toledo Rd at Brgy. Looc, Sta. 0 + 000 - Sta. 0 + 167.00, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0040 | Construction of Looc-Poblacion Seawall, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 22HO0072 | Construction of Seawall Protection Works along Santander-Balili-Toledo Road, Barangay Madridejos, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0067 | Construction of Revetment Wall at Sitio Lower Talayong, Brgy. Tupas - Sitio Bagonbon, Brgy. Libo-o (Left Side Downstream), Ronda, Cebu | FIRST GRANDEUR BUILDERS / MUANA CONST AND DEVELOPMENT CORP FORMERLY | 100.00% | DPWH |
| 23HO0189 | Construction of Storm Surge Protection Structures at Sitio Kasay, Brgy. Looc, Ginatilan, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0237 | Repair/ Rehabilitation/ Reconstruction of Damaged Alegria River Flood Control System (Upstream), Alegria, Cebu, Sta. 0+000.00 to Sta. 0+252.00 | QM BUILDERS | 100.00% | DPWH |
| 23HO0129 | Construction of Dike along Kang-actol River (Downstream), Dumanjug, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 23HO0047 | Construction of Revetment Wall at Brgy. Tapon, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0034 | Construction of Flood Control Structures, Sitio Parale - Sitio Dao (Upstream), Barangay Mindanao, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0001 | Construction of Flood Control Structure along Polo River (Downstream Left Side), Alcantara, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0040 | Construction of Flood Wall Structures along Sitio Sulok, barangay Mindanao, Malabuyoc, Cebu | GREEN WORLD CONST / MUANA CONST AND DEVELOPMENT CORP FORMERLY | 100.00% | DPWH |
| 23HO0069 | Construction of Alegria Seawall Protection Structure, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0044 | Construction of Revetment Wall along Matutinao River (Leftside), Badian, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 22HO0006 | Construction of Looc Flood Control, Ginatilan, Cebu | WORLDWIDE BUILDERS | 100.00% | DPWH |
| 23HO0147 | Construction of Dike along Kang-actol River (Left Side), Dumanjug, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 23HO0121 | Construction of Dike at Valencia River (Downstream Left Side), Alegria, Cebu | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 23HO0004 | Construction of Revetment Wall at Sitio Kang-Irong - Sitio Luwak, Brgy. Salmeron, Malabuyoc, Cebu | GICAR CONST INC | 100.00% | DPWH |
| 24HO0122 | Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu | FIRST GRANDEUR BUILDERS | 100.00% | DPWH |
| 23HO0014 | Construction of Revetment Wall at Sitio Luwak - Sitio Kang-Irong, Brgy. Salmeron, Malabuyoc, Cebu | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 23HO0162 | Construction of River Retaining Wall at Barangay Kanguha (Right Side), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0096 | Construction of Drainage System along Barangay Tunga, Moalboal, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0099 | Construction of Road Dike at Sitio Tunga - Sitio Mainit, Brgy. Montañeza, Malabuyoc | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0060 | Construction of Revetment Wall along Malbog River, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0199 | Construction of Storm Surge Protection Structures at Sitio Guilongsoran, Barangay Poblacion, Ginatilan, Cebu (Package 2) | QM BUILDERS | 100.00% | DPWH |
| 23HO0045 | Construction of Revetment Wall (Upstream) at Brgy. Tapon, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0141 | Construction of River Retaining Wall Structure at Sitio Upper Talayong, Barangay Tupas, Ronda, Cebu (Upstream) | WORLDWIDE BUILDERS | 100.00% | DPWH |
| 23HO0122 | Construction of Revetment Wall along Barangay Vive River Flood Control, Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0087 | Construction of Road Dike at Sitio Poblacion - Sitio Tunga, Brgy. Montañeza, Malabuyoc | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0088 | Construction of Road Dike at Sitio Poblacion - Sitio Galucan, Brgy. Montañeza, Malabuyoc | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0100 | Construction of River Retaining Wall Structures along Ylaya River (Brgy. Ylaya - Brgy. Poblacion), Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 23HO0124 | Construction of Riverbank Protection at Bala River (Downstream Right Side), Moalboal, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0048 | Construction of Revetment Wall along Barangay Talaba River Flood Control (Upstream), Ronda, Cebu | QM BUILDERS / FIRST GRANDEUR BUILDERS | 100.00% | DPWH |
| 23HO0202 | Construction of Storm Surge Protection Structures at Brgy. Legaspi, Alegria, Cebu (Package 3) | QM BUILDERS | 100.00% | DPWH |
| 23HO0200 | Construction of Storm Surge Protection Structures at Sitio Kalubihan, Barangay Guiwanon, Ginatilan, Cebu (Package 2) | QM BUILDERS | 100.00% | DPWH |
| 23HO0126 | Construction of Groundsill along Saliring River (Upstream), Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0144 | Construction of Revetment Wall at Barangay Vive - Barangay Tupas River Flood Control, Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0186 | Construction of Storm Surge Protection Structures at Sitio North Suba, Barangay Looc, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0140 | Construction of Revetment Wall along Sitio Elithon, Barangay Vive River Flood Control, Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0133 | Construction of Dike at Valencia River (Downstream Right Side), Alegria, Cebu | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 23HO0192 | Construction of Storm Surge Protection Strucures at Sitio Balhaan, Brgy. Looc, Ginatilan, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0123 | Construction of Riverbank Protection at Bala River (Upstream Left Side), Moalboal, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0128 | Construction of Dike along Kabalaasnan River, Dumanjug, Cebu | WORLDWIDE BUILDERS | 100.00% | DPWH |
| 23HO0187 | Construction of Storm Surge Protection Structures at Sitio Guilongsoran, Brgy. Poblacion, Ginatilan, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0203 | Construction of Storm Surge Protection Structures at Sitio Kasay, Barangay Looc, Ginatilan, Cebu (Package 2) | QM BUILDERS | 100.00% | DPWH |
| 23HO0046 | Construction of Revetment Wall along Matutinao River (Upstream), Badian, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0188 | Construcion of Storm Surge Protection Structures at Sitio Kalubihan, Brgy. Guiwanon, Ginatilan, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0193 | Construction of Storm Surge Protection Structures at Brgy. Legaspi, Alegria, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0163 | Construction of Revetment Wall at Barangay Tupas - Barangay Vive River Flood Control, Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0094 | Construction of Bank Protection Structures along Brgy. Mindanao - Brgy. Sorsogon, Malabuyoc, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0145 | Construction of River Control Structures at Bgry. Ylaya - Barangay Paculob (Upstream), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0089 | Construction of Road Dike at Brgy. Ylaya - Brgy. Libo-o, Ronda, Cebu | AR ADLAWAN CONST | 100.00% | DPWH |
| 23HO0194 | Construction of Storm Surge Protection Structures at Sitio Lutak, Brgy. Guiwanon, Ginatilan, Cebu (Package 1) | QM BUILDERS | 100.00% | DPWH |
| 23HO0035 | Construction of Flood Control Structures, Sitio Sulok-Sitio Dao (Right Side Upstream), Barangay Mindanao, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0201 | Construction of Storm Surge Protection Structures at Brgy. Legaspi, Alegria, Cebu (Package 2) | QM BUILDERS | 100.00% | DPWH |
| 23HO0146 | Construction of River Control Structure at Barangay Tubod-Dugoan (Upstream), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0093 | Construction of Revetment Wall at Barangay Libo-o - Barangay Tupas Phase 1, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 24HO0112 | Construction of Revetment Wall, Phase 2, Purok Balanghoy, Barangay Ylaya, Ronda, Cebu | RDY BUILDERS CONST AND GEN MERCHANDISE / MUANA CONST AND DEVELOPMENT CORP FORMERLY | 100.00% | DPWH |
| 23HO0002 | Construction of Flood Wall Structures along Sitio Parale (Left Side), barangay Sorsogon, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0132 | Construction of Dike at Valencia River (Upstream Left Side), Alegria, Cebu | CENTERWAYS CONST AND DEVELOPMENT INC | 100.00% | DPWH |
| 23HO0015 | Construction of Revetment Wall at Sitio Parale - Sitio Luwak, Brgy. Sorsogon - Brgy. Salmeron, Malabuyoc, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 23HO0228 | Repair/ Rehabilitation/ Reconstruction of Montañeza River Flood Control System (Upstream-Section 1), Malabuyoc, Cebu | JTC CRUZ CONST CO INC / NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0138 | Construction of Dike Strucures along Talaba River Sitio Bagonbon (Left Side), Brgy. Liboo, Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0142 | Construction of River Control Structure at Barangay Paculob - Barangay Ylaya, (Upstream), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0120 | Construction of Dike at Valencia River (Upstream Right Side), Alegria, Cebu | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0090 | Construction of Road Dike at Brgy. Libo-o - Brgy. Ylaya, Ronda, Cebu | AR ADLAWAN CONST | 100.00% | DPWH |
| 24HO0081 | Construction of Revetment along Lalao River, Malabuyoc, Cebu | GREEN WORLD CONST / MUANA CONST AND DEVELOPMENT CORP FORMERLY | 100.00% | DPWH |
| 23HO0075 | Construction of Road Dike at Purok Manga, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 24HO0095 | Construction of Revetment Wall at Barangay Tupas - Barangay Ylaya Phase 2, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 23HO0137 | Construction of Riverbank Protection along Talaba River (Sitio Upper Talayong - Sitio Cansibog), Barangay Tupas, Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0223 | Construction of Ylaya Flood Control (Upstream) (Phase II), Ylaya, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0086 | Construction of River Retaining Wall at Brgy. Kantangkas (Left Side), Dumanjug Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0148 | Construction of Riverbank Protection along Talaba River, Barangay Tupas, Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0131 | Construction of Riverbank Protection at Bala River (Upstream Right Side), Moalboal, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0149 | Rehabilitation of Riverbank along Lanao River (Downstream), Moalboal, Cebu | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0130 | Construction of Riverbank Protection at Bala River (Downstream Left Side), Moalboal, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0166 | Construction of Revetment Wall at Barangay Balaygtiki, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0236 | Repair/ Rehabilitation/ Reconstruction of Montañeza River Flood Control System (Upstream-Section 2), Malabuyoc, Cebu | JUSTBILT BUILDERS / NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 23HO0155 | Construction of Riverbank Protection along Talaba River Sitio Cansibog, Barangay Tupas, Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0231 | Repair/ Rehabilitation/ Reconstruction of Damaged Saliring River Flood Control System (Upstream), Malabuyoc, Cebu, Sta. 0+045 to Sta. 0+162 | QM BUILDERS | 100.00% | DPWH |
| 23HO0049 | Construction of Road Dike along Kabalaasnan River (Phase II), Dumanjug, Cebu | WORLDWIDE BUILDERS | 100.00% | DPWH |
| 23HO0229 | Repair/ Rehabilitation/ Reconstruction of Parale River Flood Control System (Downstream), Malabuyoc, Cebu, Sta. 0+000 to Sta. 0+131 | QM BUILDERS | 100.00% | DPWH |
| 24HO0102 | Construction of Dike, Brgy. Montañeza-Brgy. Lombo, Malabuyoc, Cebu | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 24HO0090 | Construction of Revetment Wall at Sitio Nonok - Sitio Mainit, Brgy. Montañeza, Malabuyoc, Cebu | JTC CRUZ CONST CO INC | 100.00% | DPWH |
| 23HO0177 | Construction of Riverbank Protection at Barangay Poblacion, Ginatilan (Upstream Left Side), Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 24HO0091 | Construction of Revetment Wall at Sitio Mainit - Sitio Nonok, Brgy. Montañeza, Malabuyoc, Cebu | JTC CRUZ CONST CO INC | 100.00% | DPWH |
| 24HO0099 | Construction of Revetment along Basak River (Upstream), Badian, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 23HO0076 | Construction of River Retaining Wall Structures along Ylaya River (Purok Manga Section), Brgy. Ylaya, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 23HO0178 | Construction of Riverbank Protection at Barangay Poblacion, Ginatilan (Upstream Right Side), Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 24HO0004 | Construction of Flood Control Structure, Barangay Kantangkas (Upstream), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0079 | Construction of Bank Protection Structures along Brgy. Tupas - Brgy. Butong (Right Side Downstream), Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 23HO0070 | Construction of Revetment Wall with Rechannelling Works along Polo River (Upstream), Alcantara, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0119 | Construction of Revetment Wall at Sitio Upper Talayong - Sitio Cansibog (Left Side), Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 24HO0117 | Construction of Dike at Barangay Montañeza - Barangay Lombo, Malabuyoc, Cebu | JTC CRUZ CONST CO INC | 100.00% | DPWH |
| 24HO0109 | Construction of Revetment Wall at Sitio Upper Talayong - Sitio Cansibog (Right Side), Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0025 | Construction of Revetment Wall along Montañeza (Upstream), Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0190 | Construction of Storm Surge Protection Structures at Sitio Lala-o, Barangay Montañeza, Malabuyoc, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0111 | Construction of Revetment Wall at Barangay Madridejos, Alegria, Cebu (Upstream Left Side) | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0001 | Construction of Flood Control Structure at Sitio Parale, Brgy. Sorsogon, Malabuyoc, Cebu | QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST | 100.00% | DPWH |
| 24HO0084 | Construction of Revetment Wall at Barangay Bala - Barangay Lanao (Upstream Left Side), Moalboal, Cebu | SUDAN CONST AND SUPPLY CORP | 100.00% | DPWH |
| 24HO0080 | Construction of Revetment Wall at Valencia River (Upstream Left Side), Phase 3, Alegria, Cebu | CENTERWAYS CONST AND DEVELOPMENT INC | 100.00% | DPWH |
| 23HO0239 | Repair/ Rehabilitation/ Reconstruction of Damaged Matutinao River Flood Control System (Upstream-Section 2), Badian, Cebu, Sta. 0+000.00 to sta. 0+207.00 | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 24HO0016 | Construction of Revetment Wall at Sitio Luwak, Barangay Salmeron, Malabuyoc, Cebu | GICAR CONST INC | 100.00% | DPWH |
| 23HO0026 | Construction of Revetment Wall at Sitio Luwak - Sitio Parale, Brgy. Salmeron - Brgy. Sorsogon, Malabuyoc, Cebu | SANTECH BUILDERS CORP / GICAR CONST INC | 100.00% | DPWH |
| 24HO0096 | Construction of Revetment Wall at Barangay Madridejos, Alegria, Cebu (Upstream Right Side) | FS CO BUILDERS AND SUPPLY | 100.00% | DPWH |
| 23HO0143 | Construction of Riverbank Protection along Talaba River (Sitio Cansibog - Sitio Upper Talayong), Barangay Tupas, Ronda, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 24HO0100 | Construction of Riverbank Structure at Barangay Sto. Niño - Barangay Mindanao, Malabuyoc, Cebu | JA ACHACOSO ENT & GEN SERVICES | 100.00% | DPWH |
| 23HO0238 | Repair/ Rehabilitation/ Reconstruction of Valencia River Flood Control System (Downstream), Alegria, Cebu, Sta. 0+000.00 to Sta. 0+226.00 | ZLREJ TRADING AND CONST CORP / GICAR CONST INC | 100.00% | DPWH |
| 24HO0071 | Construction of Revetment Wall along Ylaya River (Purok Manga Section), Package 3, Barangay Ylaya, Ronda, Cebu | CENTERWAYS CONST AND DEVELOPMENT INC | 100.00% | DPWH |
| 24HO0106 | Construction of Revetment Wall at Barangay Tupas - Barangay Libo-o Phase 2, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 24HO0107 | Construction of Revetment Wall at Barangay Ylaya - Barangay Tupas Phase 1, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 24HO0070 | Construction of Revetment Wall along Suba River (Palanas Side), Ginatilan, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0005 | Construction of Flood Wall Structures, Barangay Sorsogon - Barangay Salmeron (Left Side), Malabuyoc, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 24HO0094 | Construction of Revetment Wall at Barangay Salmeron - Barangay Cerdeña, Malabuyoc, Cebu | ZLREJ TRADING AND CONST CORP | 100.00% | DPWH |
| 23HO0232 | Repair/ Rehabilitation/ Reconstruction of Damaged Matutinao River Flood Control System (Upstream Section 1), Badian, Cebu, Sta. 0+000.00 to Sta. 0+182.00 | WTG CONST & DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0230 | Repair/ Rehabilitation/ Reconstruction of Ginatilan River Flood Control System, Ginatilan, Cebu, Sta. 0+000.00 to Sta. 0+130.00 | QM BUILDERS | 100.00% | DPWH |
| 23HO0092 | Construction of River Retaining Wall Structures along Ylaya River (Purok Saging - Purok Balangoy) Brgy. Ylaya, Ronda, Cebu | JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST & SUPPLY | 100.00% | DPWH |
| 23HO0225 | Construction of Drainage System along Brgy. Tunga, Moalboal, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0082 | Construction of Revetment Wall, Phase 2, Barangay Uno, Malabuyoc, Cebu | KENNETH CONST AND GEN MERCHANDISE | 100.00% | DPWH |
| 23HO0055 | Construction of Revetment Wall along Alegria River, Alegria, Cebu | QM BUILDERS | 100.00% | DPWH |
| 24HO0108 | Construction of Revetment Wall at Sitio Kanduong - Sitio Lawaan, Barangay Bala, Moalboal, Cebu | ZLREJ TRADING AND CONST CORP | 100.00% | DPWH |
| 24HO0083 | Construction of Revetment Wall at Barangay Bala - Barangay Lanao (Upstream Right Side), Moalboal, Cebu | SUDAN CONST AND SUPPLY CORP | 100.00% | DPWH |
| 23HO0119 | Rehabilitation of Riverbank along Ylaya River, Purok Manga Section, Brgy. Ylaya (Left Side), Ronda, Cebu | NEWBIG FOUR J CONST INC FORMERLY FOUR J | 100.00% | DPWH |
| 24HO0028 | Construction of Dumanjug CIS Drainage System, Dumanjug, Cebu | ADAMANT DEVELOPMENT CORP | 100.00% | DPWH |
| 23HO0016 | Construction of Flood Wall Structures, Barangay Sorsogon - Barangay Salmeron (Right Side), Malabuyoc, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0038 | Construction of Flood Wall Structures along Sitio Dao, Barangay Mindanao, Malabuyoc, Cebu | LEGACY CONST CORP FORMERLY: LEGACY CONST | 100.00% | DPWH |
| 23HO0059 | Construction of Riverbank along Ginatilan Flood Control (Upstream - Left Side) (Phase II), Ginatilan, Cebu | FIRST GRANDEUR BUILDERS / MUANA CONST AND DEVELOPMENT CORP FORMERLY | 100.00% | DPWH |
| 23HO0159 | Construction of River Retaining Wall at Barangay Lanao (Left Side), Moalboal, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0039 | Construction of Flood Wall Structures along Sitio Parale - Sitio Sulok (Left Side), barangay Mindanao, Malabuyoc, Cebu | QM BUILDERS / FIRST GRANDEUR BUILDERS | 100.00% | DPWH |
| 23HO0164 | Construction of Revetment Wall along Manlapay River (Phase 2), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0056 | Construction of Revetment Wall along Manlapay River (Section 1), Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0036 | Construction of Revetment Wall at Brgy. Colabtingon, Dumanjug, Cebu | QM BUILDERS | 100.00% | DPWH |
| 23HO0074 | Construction of River Retaining Wall at Brgy. Colabtingon (Right Side), Dumanjug, Cebu | QM BUILDERS | 99.99% | DPWH |
| 23HO0003 | Construction of Flood Wall Structures along Sitio Parale (Right Side), barangay Sorsogon, Malabuyoc, Cebu | FIRST GRANDEUR BUILDERS | 99.99% | DPWH |
| 24HO0035 | Construction of Looc-Poblacion Seawall, Dumanjug, Cebu | QM BUILDERS | 99.99% | DPWH |
| 22HO0053 | Construction of Revetment Wall along Brgy. Vive River Flood Control (Section 1), Ronda, Cebu | WTG CONST & DEVELOPMENT CORP | 98.77% | DPWH |
| 23HO0165 | Construction of River Control Structure at Barangay Pawa, Dumanjug, Cebu | QM BUILDERS | 98.50% | DPWH |
| 23HO0172 | Construction of Flood Wall Structures at Sitio Aransana - Sitio Sulok (Right Side Upstream), Brgy. Mindanao, Malabuyoc, Cebu | QG DEVELOPMENT CORP | 98.50% | DPWH |
| 22HO0002 | Construction of Ylaya Flood Control (Upstream), Ylaya, Dumanjug, Cebu | QM BUILDERS | 98.47% | DPWH |
| 23HO0240 | Repair/ Rehabilitation/ Reconstruction of Damaged Saliring River Flood Control System (Downstream), Malabuyoc, Cebu, Sta. 0+045 to Sta. 0+102 | QM BUILDERS | 98.47% | DPWH |
| 23HO0024 | Construction of Groundsill at Montañeza River, Malabuyoc, Cebu | QM BUILDERS | 3.54% | DPWH |
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Completion schedule is shown for project and contractor flags only.
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Implementing office awards near-ABC contracts far more often than the flood-control baseline
{
"office": "Cebu 7th District Engineering Office",
"nearAbc": 164,
"trigger": "office_pattern_aggregate",
"officeId": "06be37dd-f7b3-5f3f-9183-bfbc99828a72",
"threshold": 0.995,
"binomialTailP": 2.2681871697300957e-18,
"nearAbcRatePct": 96.5,
"totalContracts": 170,
"baselineRatePct": 70.4,
"excessPctPoints": 26.1,
"expectedNearAbc": 119.7,
"baselineDefinition": "share of all Sumbong flood-control contracts awarded at ≥99.5% of ABC"
}Source documents