Construction of Flood Mitigation Structure22HO0004

Construction of Poblacion Ronda Seawall, Ronda, Cebu

Construction of Poblacion Ronda Seawall, Ronda, Cebu is a DPWH-tracked public work in RONDA (CEBU), CEBU, Region VII. Reported contract value: ₱48,992,790.68. Status: Reported complete (DPWH). Contractor on record: WORLDWIDE BUILDERS / QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST. Figures trace to sumbong.

RONDA (CEBU), CEBU, Region VII
Region: Region VII

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱30,000

    Probable match · score 0.88

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0002904 · ₱1,731,307,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱47,279,312 · WORLDWIDE BUILDERS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-11-24 → 2018-11-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction of Poblacion Ronda Seawall, Ronda, Cebu

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pasil Flood Control, Oslob, Cebu
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002904

₱1,731,307,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,992,790.68

Progress

Reported complete (DPWH)

Start Date

February 10, 2022

Target End

September 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.