Rehabilitation / Major Repair of Flood Control Structure21OC0041

Rehabilitation of Slope Protection of Sapang Buwaya Creek near Annex 31 Subd., Brgy. Marcelo Green (Phase 2), Parañaque City

Rehabilitation of Slope Protection of Sapang Buwaya Creek near Annex 31 Subd., Brgy. Marcelo Green (Phase 2), Parañaque City is a DPWH-tracked public work in PARAÑAQUE CITY, National Capital Region. Reported contract value: ₱17,626,280.00. Status: Reported complete (DPWH). Contractor on record: RNN CONST CORP FORMERLY RNN CONSTRU. Figures trace to sumbong.

PARAÑAQUE CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Wall along Fortune Creek (Phase 2), Barangay Parada, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014158

₱35,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0000398

₱1,301,785.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0000333

₱318,775.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0004663

₱158,338.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

87 projects · ₱1.6B total · 1 flags

4. Implementation

Contract Amount

₱17,626,280.00

Progress

Reported complete (DPWH)

Start Date

March 22, 2022

Target End

September 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.