Flood Control and Drainage25OC0019

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAPANG BUWAYA CREEK (PHASE 2), BARANGAY SAN ANTONIO,PARAÑAQUE CITY, METRO MANILA

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAPANG BUWAYA CREEK (PHASE 2), BARANGAY SAN ANTONIO,PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱91,677,458.06. Status: Past target date (DPWH On-Going). Contractor on record: RNN CONST CORP FORMERLY RNN CONSTRU. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱30,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱91,677,458

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    78% reported · imagery 2023-07-06 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · NCR, Fourth District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAPANG BUWAYA CREEK (PHASE 2), BARANGAY SAN ANTONIO,PARAÑAQUE CITY, METRO MANILA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Don Galo River, Barangay Don Galo, Parañaque City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Flood Mitigation Structure

₱91,677,458.06 · Awardee from PhilGEPS

Award / contract ref: 25OC0019

Contractor

B

87 projects · ₱1.6B total · 1 flags

4. Implementation

Contract Amount

₱91,677,458.06

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

December 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of ParañaqueSan Antonio
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Man-Yi 2024Trami 2024Ewiniar 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.