Flood Control and Drainage21CD0061

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (LAMBAKIN SECTION) BARANGAY LAMBAKIN, SAN MIGUEL, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (LAMBAKIN SECTION) BARANGAY LAMBAKIN, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱48,998,521.59. Status: Reported complete (DPWH). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bulo River (Lambakin Section), Barangay Lambakin, San Miguel, Bulacan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bulacan 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

161 projects · ₱8.0B total · 11 flags

4. Implementation

Contract Amount

₱48,998,521.59

Progress

Reported complete (DPWH)

Start Date

March 24, 2021

Target End

November 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.