Buildings and Facilities17BD0083

LIP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, TAMARAY ST., BRGY. ATULAYAN SUR, TUGUEGARAO CITY, CAGAYAN 3RD LD

LIP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, TAMARAY ST., BRGY. ATULAYAN SUR, TUGUEGARAO CITY, CAGAYAN 3RD LD is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,879,346.50. Status: Reported complete (DPWH). Contractor on record: TOP VISION DESIGN AND CONST SERVICES. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱48,877

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0025300 · ₱5,300,000

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-02-13 → 2025-06-03

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱48,877,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Caggay Flood Control System (Downstream), Sta. 0+238 – Sta. 0+535.20, Caggay, Tuguegarao City, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0025300

₱5,300,000.00 · FY2017

Released to Regional Office - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

12 projects · ₱49.5M total · 0 flags

4. Implementation

Contract Amount

₱1,879,346.50

Progress

Reported complete (DPWH)

Start Date

April 5, 2017

Target End

July 18, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.