Flood Control and Drainage20N00095

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES OF AGUSAN RIVER BASIN (BIT-OS SECTION), BUTUAN CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES OF AGUSAN RIVER BASIN (BIT-OS SECTION), BUTUAN CITY is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱98,429,960.95. Status: Reported complete (DPWH). Contractor on record: ME 3 CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱98,429,960.95

Progress

Reported complete (DPWH)

Start Date

December 4, 2020

Target End

February 9, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.