Roads16MG0237

CONSTRUCTION OF LINED CANAL ALONG MARBEL-MAKAR CARPENTER HILL SECTION, KORONADAL CITY, SOUTH COTABATO, STA. 1701+000-STA. 1702+000

CONSTRUCTION OF LINED CANAL ALONG MARBEL-MAKAR CARPENTER HILL SECTION, KORONADAL CITY, SOUTH COTABATO, STA. 1701+000-STA. 1702+000 is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱7,981,382.00. Status: Reported complete (DPWH). Contractor on record: BETTER WORK CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱13,768,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Carpenter Hill Flood Control and drainage structures, Barangay Carpenter Hill, Koronadal City, South Cotabato
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038846

₱-10,062,870.00 · FY2016

Released to Guimaras Di (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱7,981,382.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2017

Target End

August 18, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.