Bridges, Roads19M00010

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-BANGA-TUPI-MALUNGON ROAD, (MALUNGON-TUPI SECTION), PACKAGE A, MALUNGON, SARANGANI

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-BANGA-TUPI-MALUNGON ROAD, (MALUNGON-TUPI SECTION), PACKAGE A, MALUNGON, SARANGANI is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱98,162,038.18. Status: Reported complete (DPWH). Contractor on record: ABU CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱98,162,038.18

Progress

Reported complete (DPWH)

Start Date

June 27, 2019

Target End

September 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.