Roads23CG0227

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF MEXICO -MAGALANG ROAD (NINOY AQUINO BY-WAY) INCLUDING BRIDGES,

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF MEXICO -MAGALANG ROAD (NINOY AQUINO BY-WAY) INCLUDING BRIDGES, is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱55,683,594.15. Status: Reported complete (DPWH). Contractor on record: B-12 CONST AND TRADING CORP. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.79

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23CG0227 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-10-29 → 2025-11-21

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF MEXICO -MAGALANG ROAD (NINOY AQUINO BY-WAY) INCLUDING BRIDGES,

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Quitangil River, Sta. 8+750 - Sta. 10+658 (R/S), San Agustin, Magalang, Pampanga
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱8.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2023₱156.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2020₱151.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - REHABILITATION OF STA. ANA - MAGALANG ROAD (SAN PABLO - ARENAS PORTION) PHASE I,

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DEL ROSARIO - CALULUT ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PAMPANGA 2ND LEGISLATIVE DISTRICT, PROVINCE OF PAMPANGA

Region III, Region III

2018₱132.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALINO - SUCLABAN BYPASS ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱130.7M
Past target date (DPWH On-Going)
View all 164 projects →

4. Implementation

Contract Amount

₱55,683,594.15

Progress

Reported complete (DPWH)

Start Date

July 5, 2023

Target End

July 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.