Flood Control and Drainage16C00007

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM SLOPE PROTECTION AT GUMAIN RIVER (RIGHT DIKE) UPSTREAM OF SAN PEDRO BRIDGE, FLORIDABLANCA, PAMPANGA, 2ND LEGISLATIVE DISTRICT, PAMPANGA

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM SLOPE PROTECTION AT GUMAIN RIVER (RIGHT DIKE) UPSTREAM OF SAN PEDRO BRIDGE, FLORIDABLANCA, PAMPANGA, 2ND LEGISLATIVE DISTRICT, PAMPANGA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱65,533,024.49. Status: Reported complete (DPWH). Contractor on record: TOKWING CONST CORP FOR TOKWING CONSTRUC. Figures trace to dpwh.

Region III, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

66 projects · ₱11.2B total · 0 flags

4. Implementation

Contract Amount

₱65,533,024.49

Progress

Reported complete (DPWH)

Start Date

March 25, 2016

Target End

December 19, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.