Construction of Flood Mitigation Structure21OD0142

Construction of Flood Control Wall along the Banks of Creeks in Brgy. 160, Caloocan City

Construction of Flood Control Wall along the Banks of Creeks in Brgy. 160, Caloocan City is a DPWH-tracked public work in CALOOCAN CITY, National Capital Region. Reported contract value: ₱9,548,275.07. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to sumbong.

CALOOCAN CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks in Brgy. 160, Caloocan City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010297

₱99,500,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014192

₱58,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010199

₱140,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010191

₱17,500,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013890

₱5,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013868

₱57,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱9,548,275.07

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

August 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.