Construction of Flood Mitigation Structure22EH0019

Construction/Rehabilitation of Dulangan Flood Mitigating Structure (Upstream) along Dulangan River Control, Magdiwang, Romblon

Construction/Rehabilitation of Dulangan Flood Mitigating Structure (Upstream) along Dulangan River Control, Magdiwang, Romblon is a DPWH-tracked public work in MAGDIWANG (ROMBLON), ROMBLON, Region IV-B. Reported contract value: ₱47,529,824.24. Status: Reported complete (DPWH). Contractor on record: E R DELA CRUZ CONST & SUPPLY. Figures trace to sumbong.

MAGDIWANG (ROMBLON), ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱48,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Dulangan Flood Mitigating Structure (Upstream) along Dulangan River Control, Magdiwang, Romblon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003003

₱545,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002921

₱50,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱47,529,824.24

Progress

Reported complete (DPWH)

Start Date

March 1, 2022

Target End

March 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.