Roads24N00153

CONSTRUCTION OF ACCESS ROAD LEADING TO ALTAR FALLS, PACKAGE 5, BUTUAN CITY, AGUSAN DEL NORTE

CONSTRUCTION OF ACCESS ROAD LEADING TO ALTAR FALLS, PACKAGE 5, BUTUAN CITY, AGUSAN DEL NORTE is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱96,499,824.37. Status: Past target date (DPWH On-Going). Contractor on record: ME 3 CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,824.37

Progress

Past target date (DPWH On-Going)

Start Date

September 20, 2024

Target End

August 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.