OO1 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0527 + 647 - K0528 +460, K0530 + 000 - K0532 + 000

OO1 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0527 + 647 - K0528 +460, K0530 + 000 - K0532 + 000 is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱60,870,897.53. Status: Reported complete (DPWH). Contractor on record: A3 CONST & SUPPLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Budiao-Busay River (Phase 2), Sta. 1 + 000 - Sta. 1 + 220, Daraga, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

24 projects · ₱1.6B total · 1 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS-ALBAY WEST COAST ROAD,K0554+068-K0554+598.5,K0554+756-K0555+049.5, PIO DURAN,ALBAY

Region V, Region V

2023₱144.7M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS-ALBAY WEST COAST ROAD,K0551+880-K0552+000,K0552+559-K0552+707.5, PIO DURAN,ALBAY

Region V, Region V

2023₱144.7M
Reported complete (DPWH)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TANAG-SALVACION ROAD, BARANGAY TANAG, LIBMANAN, CAMARINES

Camarines Sur 2nd DEO, Region V

2024₱138.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ROAD WIDENING - SECONDARY ROADSJCT. TAFT - ORAS - SAN POLICARPO - ARTECHE RD (S00167SM), K0965+923 - K0968+000, K0968+537 - K0969+749

Eastern Samar DEO, Region VIII

2025₱119.7M
Ongoing (DPWH-reported)

Construction of Flood Control System along Barangay Sumlang to Barangay Gapo, Camalig, Albay

CAMALIG (ALBAY), ALBAY, Region V

2024₱96.5M
Reported complete (DPWH)

Construction of Flood Mitigation and Drainage Structure along Quirangay River, Camalig, Albay (Package 1)

CAMALIG (ALBAY), ALBAY, Region V

2024₱96.5M
Reported complete (DPWH)
View all 24 projects →

4. Implementation

Contract Amount

₱60,870,897.53

Progress

Reported complete (DPWH)

Start Date

June 1, 2022

Target End

March 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.