Roads23F00064

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS-ALBAY WEST COAST ROAD,K0554+068-K0554+598.5,K0554+756-K0555+049.5, PIO DURAN,ALBAY

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS-ALBAY WEST COAST ROAD,K0554+068-K0554+598.5,K0554+756-K0555+049.5, PIO DURAN,ALBAY is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱144,749,288.24. Status: Reported complete (DPWH). Contractor on record: A3 CONST & SUPPLY. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

24 projects · ₱1.6B total · 1 flags

Other projects by this contractor

View all 24 projects →

4. Implementation

Contract Amount

₱144,749,288.24

Progress

Reported complete (DPWH)

Start Date

May 24, 2023

Target End

April 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.