Flood Control and Drainage23HF0117

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT MATAB-ANG BRIDGE (UPSTREAM) BARANGAY MATAB-ANG, TOLEDO CITY, CEBU

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT MATAB-ANG BRIDGE (UPSTREAM) BARANGAY MATAB-ANG, TOLEDO CITY, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: REBTRADE INTERNATIONAL CORP. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Camanchilles River, Barangay Talavera, Toledo City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

61 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SIBUYAN CIRCUMFERENTIAL ROAD, KO002+431-KO002+771, ROMBLON

Region IV-B, Region IV-B

2022₱259.0M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGT. PROGRAM, CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD MITIGATION STRUCTURES ALONG DUMLOG RIVER (UPSTREAM) BARANGAY CARMEN,

Region VII, Region VII

2023₱193.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-PILI-TIGAON-ALBAY BDRY RD.-K0505+700.00-K0505+970.00, SAGNAY,CAMARINES SUR 4TH LEGISLATIVE DISTRICT

Region V, Region V

2021₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BALILIHAN, BOHOL

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, PHASE 1, UBAY, BOHOL

Region VII, Region VII

2025₱188.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, MADELLA-DIANADIAWAN ROAD, PROVINCE OF AURORA

Region III, Region III

2022₱188.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

October 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.