Construction of Dike22CL0021

Construction of Maculcol River Dike, Upstream, North Approach, San Narciso, Zambales

Construction of Maculcol River Dike, Upstream, North Approach, San Narciso, Zambales is a DPWH-tracked public work in SAN NARCISO (ZAMBALES), ZAMBALES, Region III. Reported contract value: ₱48,999,754.56. Status: Reported complete (DPWH). Contractor on record: MCB ZAMORA CONST & SUPPLY. Figures trace to sumbong.

SAN NARCISO (ZAMBALES), ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Bayto River (Upstream North Approach), Sta. Cruz, Zambales
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003012

₱392,400,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002822

₱60,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001624

₱3,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

12 projects · ₱936.3M total · 1 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP); BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE /FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUITANGIL RIVER 9PHASE IV), BARANGAY TURU, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱148.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP); BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUITANGIL RIVER (PHASE I) BARANGAY ESCALER, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱148.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP); BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUITANGIL RIVER (PHASE III), BARANGAY TURU, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱148.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER SLOPE PROTECTION ALONG MAASIM RIVER, PUROK 1, BRGY. CASALAT, SAN ILDEFONSO, BULACAN (SEGMENT B)

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

Rehabilitation of Cabaoangan Creek, Subic, Zambales

SUBIC (ZAMBALES), ZAMBALES, Region III

2023₱77.2M
Reported complete (DPWH)
No sat.

Construction of Reinforced Concrete Slope Protection Structure along Quitangil Creek, Barangay San Pedro, Magalang, Pampanga

MAGALANG (PAMPANGA), PAMPANGA, Region III

2024₱77.2M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱48,999,754.56

Progress

Reported complete (DPWH)

Start Date

March 2, 2022

Target End

September 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.