Flood Control and Drainage24CL0026

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE III

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE III is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,497,246.20. Status: Past target date (DPWH On-Going). Contractor on record: AMETHYST HORIZON BUILDERS AND GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Slope Protection Works along Sto. Niño Creek, Capayawan, Botolan, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

154 projects · ₱9.6B total · 12 flags

4. Implementation

Contract Amount

₱96,497,246.20

Progress

Past target date (DPWH On-Going)

Start Date

February 16, 2024

Target End

January 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.