Roads18CE0050

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0134+375 - K0135+000, K0152+279 - K0152+872, K0160+000 - K0161+000, K0162+000 - K0163+000, K0166+662 - K0166+779, K0167+000 - K0167+224, K0173+000 - K

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT PINAGPANAAN - RIZAL - PANTABANGAN RD K0134+375 - K0135+000, K0152+279 - K0152+872, K0160+000 - K0161+000, K0162+000 - K0163+000, K0166+662 - K0166+779, K0167+000 - K0167+224, K0173+000 - K is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱32,248,461.94. Status: Reported complete (DPWH). Contractor on record: SPECO BUILDERS INC FORMERLY VRF CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Slope Protection with Steel Sheet Pile along Talavera River, Brgy. Maestrang Kikay, Talavera, Nueva Ecija
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-18-0019535

₱17,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱32,248,461.94

Progress

Reported complete (DPWH)

Start Date

April 27, 2018

Target End

September 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.