GAA 2025 OO-225CE0148

CONSTRUCTION OF DE LEON DAM, BARANGAY BULAC, TALAVERA, NUEVA ECIJA

CONSTRUCTION OF DE LEON DAM, BARANGAY BULAC, TALAVERA, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱116,407,423.31. Status: Past target date (DPWH On-Going). Contractor on record: SPECO BUILDERS INC FORMERLY VRF CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱41,836,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Talavera River, Barangay Calipahan, Talavera, Nueva Ecija
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Nueva Ecija 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

131 projects · ₱6.2B total · 3 flags

4. Implementation

Contract Amount

₱116,407,423.31

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

December 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.