GAA 2025 OO-125JJ0010

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882 is a DPWH-tracked public work in Zamboanga del Norte 4th DEO, Region IX. Reported contract value: ₱16,445,379.59. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BENRAM CONST. Figures trace to dpwh.

Zamboanga del Norte 4th DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Mamad, Baliguian, Zamboanga del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zamboanga del Norte 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

53 projects · ₱2.6B total · 0 flags

4. Implementation

Contract Amount

₱16,445,379.59

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2025

Target End

October 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.