Roads24JJ0008

PREVENTIVE MAINTENANCE - SECONDARY ROADS, SIOCON- SIRAWAI- SIBUCO- LIMPAPA RD- K2098 + 000 - K2102 + 300

PREVENTIVE MAINTENANCE - SECONDARY ROADS, SIOCON- SIRAWAI- SIBUCO- LIMPAPA RD- K2098 + 000 - K2102 + 300 is a DPWH-tracked public work in Zamboanga del Norte 4th DEO, Region IX. Reported contract value: ₱118,912,125.00. Status: Past target date (DPWH On-Going). Contractor on record: BENRAM CONST. Figures trace to dpwh.

Zamboanga del Norte 4th DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱31,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion, Polanco, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zamboanga del Norte 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱118,912,125.00

Progress

Past target date (DPWH On-Going)

Start Date

February 14, 2024

Target End

October 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.