Flood Control and Drainage23CL0084

CONSTRUCTION OF SLOPE PROTECTION AT LAWIS RIVER, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 4)

CONSTRUCTION OF SLOPE PROTECTION AT LAWIS RIVER, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 4) is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱98,999,368.00. Status: Reported complete (DPWH). Contractor on record: JTC CRUZ CONST CO INC. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱98,009,500 · JTC CRUZ CONST CO INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-01-30 → 2024-02-19

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Zambales

Based on the coordinates published with the DPWH record and NOAH file Zambales.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF SLOPE PROTECTION AT LAWIS RIVER, UPSTREAM, CANDELARIA, ZAMBALES (PHASE 4)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Bayto River, North Approach, Santa Cruz, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23CL0084 - LAWIS RIVER, UPSTREAM (PHASE 4)

₱98,009,500.22 · JTC CRUZ CONST CO INC

Award / contract ref: 23CL0084

Contractor

B

154 projects · ₱8.5B total · 5 flags

4. Implementation

Contract Amount

₱98,999,368.00

Progress

Reported complete (DPWH)

Start Date

April 17, 2023

Target End

March 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.