Buildings and Facilities18CM0090

CONSTRUCTION OF CLASSROOMS, 2-UNITS, 2-STOREY, 4-CLASSROOMS SCHOOL BUILDING NEW CABALAN NATIONAL HIGH SCHOOL, OLONGAPO CITY

CONSTRUCTION OF CLASSROOMS, 2-UNITS, 2-STOREY, 4-CLASSROOMS SCHOOL BUILDING NEW CABALAN NATIONAL HIGH SCHOOL, OLONGAPO CITY is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱19,250,398.72. Status: Reported complete (DPWH). Contractor on record: JAMJLE PROPERTIES SUBIC AND DEVELOPMENT CORPORAT. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱50,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0022785 ·

    Possible match · score 0.80

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-03-24 → 2019-10-27

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Cabalan River, Olongapo City, Zambales
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0022785

₱0.00 · FY2018

Released to Division of Zambales (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,250,398.72

Progress

Reported complete (DPWH)

Start Date

August 30, 2018

Target End

August 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.