Roads24EE0098

CONSTRUCTION/IMPROVEMENT OF NEW QUEZON-CHEEY-SAN JOSE-DECALACHAO ROAD LEADING TO BUSUANGA AIRPORT, BUSUANGA, PALAWAN

CONSTRUCTION/IMPROVEMENT OF NEW QUEZON-CHEEY-SAN JOSE-DECALACHAO ROAD LEADING TO BUSUANGA AIRPORT, BUSUANGA, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱9,799,595.57. Status: Reported complete (DPWH). Contractor on record: ALPHA VECTOR CONST AND SUPPLY. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bono - Bono River Flood Control Structure, Bataraza, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Palawan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24EE0098-Construction/Improvement of New Quezon

₱9,784,765.52 · ALPHA VECTOR CONSTRUCTION AND SUPPLY

Contractor

99 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY IN

Batangas 4th DEO, Region IV-A

2024₱144.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY INTERCHANGE PACKAGE C, BUGTONG NA PULO, LIPA CITY, BATANGA

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- TERTIARY ROADS- CORON-BUSUANGA ROAD, K0059+866-K0061+205, CORON, PALAWAN

Region IV-B, Region IV-B

2023₱101.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG

Batangas 4th DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANABA BRIDGE BUSUANGA, PALAWAN

Palawan 1st DEO, Region IV-B

2024₱96.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF SLOPE PROTECTION STRUCTURE (KIWIT BR. 1), BUSUANGA, PALAWAN

Region IV-B, Region IV-B

2025₱72.5M
Past target date (DPWH On-Going)
View all 99 projects →

4. Implementation

Contract Amount

₱9,799,595.57

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

May 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.