Flood Control and Drainage23DN0047

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH BOX CULVERT, BARANGAY BAGONG NAYON, ANTIPOLO CITY (FIRST DISTRICT)

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH BOX CULVERT, BARANGAY BAGONG NAYON, ANTIPOLO CITY (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱30,719,412.14. Status: Past target date (DPWH On-Going). Contractor on record: LTDL BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱33,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱30,719,412 · LTDL BUILDERS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    94% reported · imagery 2021-02-25 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Rizal

Based on the coordinates published with the DPWH record and NOAH file Rizal.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH BOX CULVERT, BARANGAY BAGONG NAYON, ANTIPOLO CITY (FIRST DISTRICT)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱33,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure with Box Culvert, Barangay Bagong Nayon, Antipolo City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Rizal 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23DN0047

₱30,719,412.14 · LTDL BUILDERS

Award / contract ref: 23DN0047

Contractor

C

195 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱30,719,412.14

Progress

Past target date (DPWH On-Going)

Start Date

February 23, 2023

Target End

October 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.