Roads20PE0043

CONSTRUCTION OF CONCRETE ROAD - ALONG CAWAYAN-CALEW-BALOCOC-CASHET ROAD TO SAN MANUEL, PANGASINAN IN SUPPORT TO COFFEE, CACAO,BAMBOO, BANANA, LIVESTOCK, HEIRLOOM RICE, GOLD, HIGH VALUE VEGETABLES, LOOM WEAVING, SEWING, DRESS MAKING, HONEY, FOOD PROCESSI

CONSTRUCTION OF CONCRETE ROAD - ALONG CAWAYAN-CALEW-BALOCOC-CASHET ROAD TO SAN MANUEL, PANGASINAN IN SUPPORT TO COFFEE, CACAO,BAMBOO, BANANA, LIVESTOCK, HEIRLOOM RICE, GOLD, HIGH VALUE VEGETABLES, LOOM WEAVING, SEWING, DRESS MAKING, HONEY, FOOD PROCESSI is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱9,701,764.11. Status: Reported complete (DPWH). Contractor on record: AKSUM CONTRACTING CORP. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Agno River Basin, Ekip Section, Bokod, Benguet
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Benguet 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

14 projects · ₱1.1B total · 2 flags

4. Implementation

Contract Amount

₱9,701,764.11

Progress

Reported complete (DPWH)

Start Date

March 16, 2020

Target End

September 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.