Water Provision and Storage23DD0309

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III), CONSTRUCTION/COMPLETION OF WATER SUPPLY SYSTEM IN BRGY. BIGAIN 2, SAN JOSE, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III), CONSTRUCTION/COMPLETION OF WATER SUPPLY SYSTEM IN BRGY. BIGAIN 2, SAN JOSE, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱3,841,200.00. Status: Reported complete (DPWH). Contractor on record: TONIJON CONST AND DEVELOPMENT INC FORMERLY: TONIJON CONST. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱6,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23DD0309 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-28 → 2025-08-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III), CONSTRUCTION/COMPLETION OF WATER SUPPLY SYSTEM IN BRGY. BIGAIN 2, SAN JOSE, BATANGAS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Box Culvert, Cultihan Road, Barangay Salaban, San Jose, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

101 projects · ₱661.0M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PINAGBAYANAN, TAYSAN, BATA

Batangas 4th DEO, Region IV-A

2024₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

Construction of Flood Control Structure, Paninsingin Bridge, Rosario, Batangas

ROSARIO (BATANGAS), BATANGAS, Region IV-A

2023₱29.4M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas

ROSARIO (BATANGAS), BATANGAS, Region IV-A

2023₱29.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAHANADIONG BRIDGE, TAYSAN

Batangas 4th DEO, Region IV-A

2024₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, OFF - CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, SN JUAN-LAIYA RD - K0151 + 510 - K0151 + 808, K0151 + 815 - K0152 + 940

Batangas 4th DEO, Region IV-A

2022₱22.3M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION OF ROAD WITH LINE CANAL AT BRGY. CAWONGAN AND POBLACION, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2019₱19.0M
Reported complete (DPWH)
View all 101 projects →

4. Implementation

Contract Amount

₱3,841,200.00

Progress

Reported complete (DPWH)

Start Date

August 17, 2023

Target End

October 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.