Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23BB0156 was awarded at 99.97% of its ABC. Across its 24 recorded contracts, TJMT CONST was awarded at ≥99.5% of ABC 23 times (95.8%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids very close to the ABC to maximize their chances of winning within legal limits.

Public record entityRehabilitation of Flood Control Structure, Baraccaoit, Gattaran, Cagayan Package III - Sta. 0+777 - Sta. 1+253
LocationGATTARAN (CAGAYAN), CAGAYAN, Region IIContract 23BB0156
Amount₱72,353,000.0099.97% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Rehabilitation of Flood Control Structure, Baraccaoit, Gattaran, Cagayan Package III - Sta. 0+777 - Sta. 1+25323BB0156Flood control100%April 22, 2024April 22, 2024—completedsumbong source

Start: June 8, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Cagayan 1st District Engineering Office",
  "ratio": 0.9996960276338515,
  "abcPhp": 72375000,
  "threshold": 0.995,
  "contractId": "23BB0156",
  "contractor": "TJMT CONST",
  "contractCostPhp": 72353000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate