Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 5 contracts awarded to ST MATTHEW GEN CONTRACTOR & DEVELOPMENT CORP by the same office started within 0 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 5 in the same municipality. These may be separate flood control projects at different sites within the same municipality, each requiring its own contract.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure along Dongdong River (Left Bank), Barangay Acnam, Sitio Saranay, Nueva Era, Ilocos Norte22A00281Flood control | 100% | May 1, 2023 | March 15, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: November 3, 2022 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold in one municipality
{
"deo": "Ilocos Norte 2nd District Engineering Office",
"contractId": "22A00281",
"contractor": "ST MATTHEW GEN CONTRACTOR & DEVELOPMENT CORP",
"windowDays": 120,
"clusterSize": 5,
"thresholdPhp": 50000000,
"contractCostPhp": 48249999.1,
"maxInOneMunicipality": 5
}Source documents