High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: SILVERWOLVES CONST CORP holds 29 flood-control contracts worth ₱3.18B, 3.13× the 95th-percentile contractor total (₱1.01B); up to 15 ran at the same time. This is a capacity question worth examining. The contractor may have specialized expertise or capacity that justifies handling a large number of projects.

Public record entitySILVERWOLVES CONST CORPOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 29Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Riverbank Structure along Agno and Allied Rivers, Alcala, Pangasinan24A00493Flood control100%December 4, 2024July 31, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Riverbank Structure along Aloragat and Allied Rivers, Package 2, Binalonan -Laoac, Pangasinan24A00453Flood control100%January 12, 2025January 12, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Aringay River, Barangay Samara-Sta.Lucia, Aringay, La Union24A00438Flood control100%January 18, 2025September 2, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 1), Bauang, La Union24AF0108Flood control100%January 4, 2025January 6, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 2), Bauang, La Union24AF0109Flood control100%January 4, 2025January 6, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 3), Bauang, La Union24AF0110Flood control100%January 4, 2025March 16, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Show 23 more projects in this bucket
Construction of Flood Control structure along Bauang River Basin (Package 4), Bauang, La Union24AF0111Flood control100%January 4, 2025March 16, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 5), Bauang, La Union24AF0112Flood control100%January 4, 2025March 16, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 6), Bauang, La Union24AF0113Flood control100%January 4, 2025March 16, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control structure along Bauang River Basin (Package 7), Bauang, La Union24AF0114Flood control100%January 4, 2025March 16, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Ribsuan River, Barangay Ribsuan, Naguilian, La Union24A00347Flood control100%February 2, 2025November 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Aringay River Basin, Aringay, La Union (Package 1)23AF0100Flood control100%December 10, 2023February 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Aringay River Basin, Aringay, La Union (Package 2)23AF0101Flood control100%December 10, 2023February 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Aringay River Basin, Aringay, La Union (Package 3)23AF0102Flood control100%December 10, 2023February 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Aringay River Basin, Aringay, La Union (Package 4)23AF0103Flood control100%December 10, 2023February 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Principe River, Agoo, La Union (Package 1)23A00268Flood control100%April 5, 2024April 5, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along the Principe River, Agoo, La Union (Package 2)23A00269Flood control100%April 5, 2024April 5, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Maluyo River, Barangay Sablut, Balaoan, La Union24A00487Flood control100%December 29, 2024December 29, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Sinucalan River, Barangay Camantiles, Urdaneta, Pangasinan24A00349Flood control100%April 19, 2025November 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Mag-asawang Tubig River Control along Brgy. Pinagsabangan II, Naujan, Oriental Mindoro24ED0125Flood control100%September 23, 2024May 21, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Control Structure Along Catuiran River, Sitio Duluhan Section, Brgy. Arangin, Naujan, Oriental Mindoro24ED0066Flood control100%February 17, 2025April 22, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Control Structure along Mag-Asawang Tubig River Sitio Pantaunan, Brgy. Bagong Buhay, Naujan, Oriental Mindoro24ED0069Flood control100%February 17, 2025April 19, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Control Structure Along Panggalaan River, Brgy. San Nicolas, Naujan, Oriental Mindoro24ED0067Flood control100%February 17, 2025March 26, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Control Structure along Panggalaan River, Brgy. Tigkan, Naujan, Oriental Mindoro24ED0068Flood control100%February 17, 2025May 8, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Talenceras Flood Control at Talenceras, Tubigon, Bohol24HA0001Flood control100%February 22, 2025February 22, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Flood Control Structure along Agos River, Infanta, Quezon (Package A)23D00139Flood control100%April 9, 2024April 9, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Flood Control Structure along Agos River, Infanta, Quezon (Package B)23D00140Flood control100%April 9, 2024April 9, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Dike along Dulangan River, Evangelista Section, Naujan, Oriental Mindoro23E00165100%April 6, 2024October 15, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Dike along Dulangan River, Paetan Section, Naujan, Oriental Mindoro23E00166100%April 6, 2024October 15, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "SILVERWOLVES CONST CORP",
  "projectCount": 29,
  "totalValuePhp": 3175616141.390001,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name

Connected records

Where this contractor works

Contractor grade C23 storms reached its projects · typhoon modeAll contractors & gradesContractor patterns