Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 25HN0043 (₱72.33M) is recorded as completed in 66 days against 254 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.3%. The contractor may have deployed unusually large resources or worked in favorable conditions, allowing for rapid completion.

Public record entityConstruction of Flood Control Structure along Butuanon River (Downstream) Outfall, Barangay Pakna-an, Mandaue City, Cebu
LocationMANDAUE CITY (CEBU), CEBU, Region VIIContract 25HN0043
Amount₱72,325,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Butuanon River (Downstream) Outfall, Barangay Pakna-an, Mandaue City, Cebu25HN0043Flood control100%November 2, 2025April 28, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 21, 2025 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2025-02-21T00:00:00.000Z",
  "contractId": "25HN0043",
  "actualEndDate": "2025-04-28T00:00:00.000Z",
  "targetEndDate": "2025-11-01T00:00:00.000Z",
  "contractCostPhp": 72325000
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)City of MandauePakna-an
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025
Hazard exposure
Active fault9.2 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgeinundated from SSA3 (4.01-5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.