Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23PA0104 was awarded at 100.00% of its ABC. Across its 44 recorded contracts, MG SAMIDAN CONST was awarded at ≥99.5% of ABC 42 times (95.5%), versus 70.4% for flood-control contracts overall. It is possible that the contractor bid exactly at the ABC to maximize their chance of winning within legal limits.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure along Abra Major River Basin, Barangay Nagtupacan, Dolores, Abra23PA0104Flood control | 100% | March 21, 2024 | April 10, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: April 14, 2023 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Abra District Engineering Office",
"ratio": 0.9999628407361592,
"abcPhp": 144749907.4,
"threshold": 0.995,
"contractId": "23PA0104",
"contractor": "MG SAMIDAN CONST",
"contractCostPhp": 144744528.6
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate