Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 25HL0025 (₱48.85M) is recorded as completed in 62 days against 209 planned; similar-cost projects take a median of 239 days, putting it in the fastest 1.5%. This could be due to unusually efficient work, favorable weather, or early completion of preparatory activities.

Public record entityConstruction of Flood Control Structure, Amio River (Downstream), Package 1, Santa Catalina, Negros Oriental
LocationSANTA CATALINA (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VIIContract 25HL0025
Amount₱48,852,510.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure, Amio River (Downstream), Package 1, Santa Catalina, Negros Oriental25HL0025Flood control100%September 16, 2025April 22, 2025—completedsumbong source

Start: February 19, 2025 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2025-02-19T00:00:00.000Z",
  "contractId": "25HL0025",
  "actualEndDate": "2025-04-22T00:00:00.000Z",
  "targetEndDate": "2025-09-15T00:00:00.000Z",
  "contractCostPhp": 48852510
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo
  • This could be due to unusually efficient work, favorable weather, or early completion of preparatory activities.