High Concurrent Workload for One Contractor
Contractor linked to many simultaneous projects or very high total value vs peers.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST holds 32 flood-control contracts worth ₱2.51B, 2.47× the 95th-percentile contractor total (₱1.01B); up to 14 ran at the same time. This is a capacity question worth examining. The contractor may have specialized expertise or capacity that led to being awarded many projects.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Dalaguete River Flood Control, Dalaguete, Cebu22HG0020Flood control | 100% | October 21, 2022 | October 14, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Dike along Kang-actol River (Downstream), Dumanjug, Cebu23HO0129Flood control | 100% | February 11, 2024 | December 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Dike along Kang-actol River (Left Side), Dumanjug, Cebu23HO0147Flood control | 100% | February 11, 2024 | December 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Basak Creek, Mandaue City, Cebu23HN0056Flood control | 100% | January 7, 2024 | January 7, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Basak Creek, Mandaue City, Cebu, Phase II23HN0114Flood control | 100% | November 13, 2024 | April 4, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Bawo River, Catmon-Side, Catmon, Cebu23H00070Flood control | 100% | January 21, 2024 | December 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Show 26 more projects in this bucket
| Construction of Flood Control Structure along Butuanon River (Phase IX) Upstream, Brgy. Tabok, Mandaue City, Cebu23HN0113Flood control | 100% | April 12, 2024 | February 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Butuanon River (Phase VII), Mandaue City, Cebu23HN0049Flood control | 100% | March 13, 2024 | December 12, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Butuanon River Upstream, Barangay Maguikay, Mandaue City, Cebu23HN0128Flood control | 100% | April 12, 2024 | November 29, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Cansaga River with Box Culvert, Barangay Danglag, Consolacion, Cebu22HN0008Flood control | 100% | December 8, 2022 | December 8, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Cansaga River, Barangay Garing, Phase 3, Consolacion, Cebu24HN0024Flood control | 100% | August 11, 2024 | August 9, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Panalipan River (Upstream), Catmon, Cebu24HI0001Flood control | 100% | November 11, 2024 | November 11, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Panalipan River, Catmon, Cebu22HI0018Flood control | 100% | December 1, 2022 | December 1, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure along Panalipan River, Catmon, Cebu23HI0002Flood control | 100% | August 27, 2023 | August 27, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure at Sitio Parale, Brgy. Sorsogon, Malabuyoc, Cebu23HO0001Flood control | 100% | December 18, 2023 | September 26, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Mananga River, Sta. 0+000 - Sta. 0+331 (both side), Talisay City, Cebu22HE0033Flood control | 100% | December 19, 2022 | December 19, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structures at Brgy Lanas, Naga City, Cebu (Package 1) Left Side24HE0160Flood control | 100% | December 25, 2024 | October 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structures at Brgy Lanas, Naga City, Cebu (Package 2) Right Side24HE0159Flood control | 100% | December 25, 2024 | September 20, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Mananga River (Upper Side), Talisay City, Cebu22H00041Flood control | 100% | May 16, 2023 | December 15, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Lamacan River Flood Control Structure (Downstream), Sta. 0 + 000 - Sta. 0 + 230 (Leftside), Sta. 0 + 000 - Sta. 0 + 230 (Rightside), Sibonga, Cebu23HE0110Flood control | 100% | January 13, 2024 | November 21, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Mananga River Flood Control Structure, Talisay City, Cebu23HE0097Flood control | 100% | January 6, 2024 | September 11, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Revetment along Basak River (Upstream), Badian, Cebu24HO0099Flood control | 100% | October 22, 2024 | October 22, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of River Capacity Enhancement Structure along Butuanon River, Barangay Casuntingan-Barangay Cabancalan, Mandaue City, Cebu, (Phase 6)24HN0090Flood control | 100% | January 15, 2025 | August 19, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of San Isidro River Flood Control Structure, San Fernando, Cebu21HE0157Flood control | 100% | August 1, 2022 | August 1, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall, Brgy. Cansojong, Talisay City, Cebu22HE0067Flood control | 100% | August 30, 2022 | August 30, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall, Brgy. Poblacion, Talisay City, Cebu22HE0066Flood control | 100% | December 21, 2022 | December 21, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Seawall, Brgy. Tangke, Talisay City, Cebu22HE0068Flood control | 100% | October 1, 2022 | September 30, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Tina-An River Flood Control Structure, Naga City, Cebu21HE0156Flood control | 100% | August 1, 2022 | August 1, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction/Improvement of Flood Control Structure along Butuanon River, Brgy. Tabok, Mandaue City, Cebu23HN0071Flood control | 100% | April 11, 2024 | November 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Revetment Wall at Sitio Parale - Sitio Luwak, Brgy. Sorsogon - Brgy. Salmeron, Malabuyoc, Cebu23HO0015 | 100% | December 19, 2023 | September 26, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Road Dike along Kang-actol River, Damanjug, Cebu22HO0066 | 100% | October 24, 2022 | October 24, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Slope Protection Structure along Natalio Bacalso Avenue, Dalaguete, Cebu22HG0044 | 100% | October 21, 2022 | October 21, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Rule Definition
Active project count and total value vs peer 95th percentile.
Triggering Data & citations
Contractor carries far more concurrent flood-control value than peers
{
"contractor": "QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST",
"projectCount": 32,
"totalValuePhp": 2509859531.91,
"peerP95TotalPhp": 1014143494.4100002,
"activeProjectCount": 0,
"simultaneousThreshold": 25
}Source documents
Possible Innocent Explanations
- Large national firm with many concurrent government clients
- Data groups joint ventures under one name