Construction of Flood Mitigation Structure21HE0157

Construction of San Isidro River Flood Control Structure, San Fernando, Cebu

Construction of San Isidro River Flood Control Structure, San Fernando, Cebu is a DPWH-tracked public work in CEBU, Region VII. Reported contract value: ₱77,200,000.00. Status: Reported complete (DPWH). Contractor on record: QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST. Figures trace to sumbong.

CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Avante Bridge, San Remigio, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014115

₱22,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013821

₱19,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21HE0157

₱74,884,888.00 · QUIRANTE CONSTRUCTION

Contractor

B

409 projects · ₱18.8B total · 42 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF COASTAL ROAD, PHASE 1, BARANGAY IBO, LAPULAPU CITY, CEBU

Region VII, Region VII

2024₱231.5M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TIPOLO RIVER, PHASE 4, MANDAUE CITY

Region VII, Region VII

2025₱202.5M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANTAYUPAN ROAD (LEADING TO BANGAG LAPOS CAVE), BARILI, CEBU

Region VII, Region VII

2024₱178.2M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF FLOOD CONTROL STRUCTURE ALONG MANANGA RIVER (UPSTREAM), TALISAY CITY, CEBU

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BABAG-BASAK-SUBABASBAS BYPASS ROAD, LAPU-LAPU CITY

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MARIGONDON-BASAK BYPASS ROAD, LAPU-LAPU CITY, CEBU

Region VII, Region VII

2024₱173.6M
Past target date (DPWH On-Going)
View all 409 projects →

4. Implementation

Contract Amount

₱77,200,000.00

Progress

Reported complete (DPWH)

Start Date

November 3, 2021

Target End

August 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.