Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: Butuan City District Engineering Office awarded 48 of 48 recorded flood-control contracts (100.0%) at 99.5% or more of their Approved Budget for the Contract, versus 70.4% for flood-control contracts nationwide (29.6 percentage points higher; binomial p = 4.8e-08), across 15 contractors. Source: DPWH / Sumbong sa Pangulo contract records; each contract is listed below. This may be due to highly competitive bidding where contractors consistently bid close to the ABC.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Butuan City District Engineering Office: contracts
48 of 48 contracts (100%) at ≥99.5% of ABC · peer baseline 70.4% · gap +29.6 pts · binomial p = 4.8e-8. Source: DPWH transparency portal and Sumbong sa Pangulo records (linked per contract).
| Contract | Title | Contractor | % of ABC | Source |
|---|---|---|---|---|
| 22ND0031 | Construction of Main Drainage Canal, NRJ BCIR to LADP Creek, Employees Village, Butuan City, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 24ND0078 | Construction / Maintenance of Flood Mitigation Structures and Drainage System-Flood Mitigation Structures at Masao Rivermouth and Construction of Cut-off Channe | ADFIL CORP | 100.00% | DPWH |
| 24ND0019 | Construction of Drainage, Barangay Bayanihan, Butuan City, Agusan del Norte | FHD CONST AND SUPPLY | 100.00% | DPWH |
| 23N00109 | Construction of Drainage System along Butuan City-Cagayan de Oro-Iligan Road, Butuan City Airport to Libertad Bridge (Both Sides) including sidewalk, curb and g | ME 3 CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 24ND0064 | Construction of Flood Mitigation Structure along Obod-obod Creek, Package 2, Butuan City, Agusan del Norte | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 22ND0030 | Construction of Main Drainage Canal, NRJ BCIR to Provincial Hospital to LADP, Butuan City, Agusan del Norte | ME 3 CONST | 100.00% | DPWH |
| 23N00186 | Rehabilitation of Dike along Mandakpan-Bonbon Channel, Downstream Section, Butuan City, Agusan Del Norte | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 23ND0037 | Construction of River Bank Protection at Pianing Bridge along Butuan City-Pianing-Tandag Rd, Butuan City, Agusan del Norte | NORTHERN BUILDERS | 100.00% | DPWH |
| 23N00108 | Construction of Drainage along Jollibee Downtown to Gaisano Mall (Both Sides) including sidewalk, curb and gutter, Butuan City, Agusan Del Norte | ME 3 CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 23N00110 | Construction of Drainage System along Butuan City-Cagayan de Oro-Iligan Road, Libertad Bridge to Robinsons (Both Sides) including sidewalk, curb and gutter, But | ME 3 CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 24ND0113 | Rehabilitation of Flood Control Drainage System of Lower Agusan Development Project, Langihan Creek Section, Butuan City, Agusan del Norte | RAMISES CONST | 100.00% | DPWH |
| 23N00118 | Rehabilitation of Bank Protection Structure along Taguibo River Protecting Taguibo Dam Water-Filtration Facilities, Package 1, Barangay Anticala, Butuan City, A | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 24N00088 | Rehabilitation of Bank Protection Structure along Taguibo River Protecting Taguibo Dam Water-Filtration Facilities, Package 2, Barangay Anticala, Butuan City, A | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 22N00092 | Construction of Bank Protection along Agusan River, Agusan Pequeño Section, Package 1, Butuan City, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 23N00107 | Construction of Drainage along Butuan City- Cagayan de Oro-Iligan Road, DBP TO Robinsons Mall R/S including sidewalk, curb and gutter, Butuan City, Agusan Del N | RAMISES CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 23N00113 | Construction of Flood Mitigation Structure along Obod-obod Creek, Package 1, Butuan City, Agusan del Norte | ME 3 CONST | 100.00% | DPWH |
| 24ND0039 | Construction of Flood Mitigation Structure along Agusan River (Dankias Section) Package 1, Butuan City | ME 3 CONST | 100.00% | DPWH |
| 22N00095 | Construction of Flood Mitigation Structure along Banza River at Banza Ruins Section, Butuan City, Agusan del Norte | ME 3 CONST | 100.00% | DPWH |
| 23N00112 | Construction of Flood Control Structure - Lower Agusan Development Project, Flood Control (Bancasi Bridge Revetment Upstream and Downstream, Butuan City, Agusan | RAMISES CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 24N00130 | Construction of Flood Control Structure - Lower Agusan Development Project, Flood Control (Bancasi Bridge Revetment Upstream and Downstream), Package 2, Butuan | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 22N00132 | Construction of Flood Control Mitigation Structure along Agusan River Basin Protecting Barangay Poblacion, Las Nieves, Package 1, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 23N00119 | Rehabilitation of Bank Protection Structure along Taguibo River Protecting Taguibo Dam Water-Filtration Facilities, Package 2, Barangay Anticala, Butuan City, A | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 23N00116 | Construction of Riverbank Protection at Magsaysay Bridge, 1st Approach, Butuan City, Agusan Del Norte | EQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 22ND0057 | Construction of Flood Control Structure along Tagabaca-Aupagan, Phase 1, Butuan City | NORTHERN BUILDERS | 100.00% | DPWH |
| 22N00094 | Construction of Flood Control Structures at Weighbridge Section, Package 1, Ampayon, Butuan City, Agusan del Norte | RAMISES CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 22N00097 | Construction of Main Drainage Canal along Capitol - Bonbon Road to C.T. Montalban St. to Villa Kananga Creek, Butuan City, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 23N00164 | Construction of Bank Protection along Agusan River, Agusan Pequeño Section, Package 2, Butuan City, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 23N00111 | Construction of Drainage System along Butuan City-Cagayan de Oro-Iligan Road, Silongan St. to Jct Montilla Blvd (Both Sides) including sidewalk, curb and gutter | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 23N00114 | Construction of Flood Mitigation Structure along Tagabaka Creek, Downstream with RCBC Improvement, Butuan City, Agusan del Norte | ME 3 CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 21ND0106 | Rehabilitation of National Roads with Slips, Slope Collapse and Landslide along Daang Maharlika Road - K1240+500 - K1240+746.60, Butuan City | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 24ND0024 | Construction of Larpis Slope Protection Works, Butuan City, Agusan del Norte | ADFIL CORP | 100.00% | DPWH |
| 22N00190 | Rehabilitation of Bank Protection Structure along Taguibo River Protecting Taguibo Dam Water-Filtration Facilities, Brgy. Anticala, Butuan City | EQUI-PARCO CONST CO / TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 23N00115 | Construction of Flood Mitigation Structures at NRJ Villa Paraiso Section to Barangay Antongalon, Butuan City, Agusan del Norte | RAMISES CONST | 100.00% | DPWH |
| 22N00098 | Construction of Main Drainage Canal along Jct. Montilla Boulevard - Salvador Calo Street to LADP Main Drainage Canal, Butuan City, Agusan del Norte | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 22N00096 | Construction of Main Drainage Canal along BCIR - JCT Rosales Avenue - LADP CARBDP Main Drainage Channel (Barangay Imadejas to Barangay Libertad) Package 1, Butu | M MONTESCLAROS ENT INC | 100.00% | DPWH |
| 24N00140 | Rehabilitation of Flood Control Structure along Malalag - Libertad Section, Package 2, Butuan City, Agusan del Norte | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 23N00084 | Construction (Completion) of Main Drainage Canal Along Montilla JCT Montilla Boulevard - Salvador Calo Street to Main LADP Main Drainage Canal Butuan City, Agus | EQUI-PARCO CONST CO | 100.00% | DPWH |
| 21N00094 | Construction of Flood Mitigation Structures along Agusan River (Tungao Section) Package 1, Butuan City, Agusan del Norte | ME 3 CONST | 100.00% | DPWH |
| 23N00085 | Construction of Main Drainage Canal Along JCT Montilla Boulevard - T. Calo Street - NRJ BCIR to Main LADP Main Drainage Canal (T. Calo - Ochoa Section), Butuan | ADFIL CORP | 100.00% | DPWH |
| 23N00097 | Construction of Flood Mitigation Structure along Agusan River (Ambacon Section) Upstream, Las Nieves, Agusan del Norte | ME 3 CONST / EVENPAR CONST AND DEVELOPMENT CORP FORMERLY: EVEN PAR CONST CO INC | 100.00% | DPWH |
| 23N00123 | Construction of Main Drainage Canal along Montilla JCT BCIR - South Montilla Boulevard - LADP Main Drainage Canal Package 1, Butuan City, Agusan del Norte | ME 3 CONST / EQUI-PARCO CONST CO | 100.00% | DPWH |
| 24N00134 | Rehabilitation of Flood Control Structure along Malalag - Libertad Section, Package 1, Butuan City, Agusan del Norte | TRIPARCO DEVELOPMENT CORP | 100.00% | DPWH |
| 23N00096 | Construction of Flood Mitigation Structure along Agusan River (Ambacon Section) Downstream, Las Nieves, Agusan del Norte | ME 3 CONST / EVENPAR CONST AND DEVELOPMENT CORP FORMERLY: EVEN PAR CONST CO INC | 100.00% | DPWH |
| 22N00110 | Construction of Flood Mitigation Structure along Agusan River (Tungao Section) Package 2, Sta. 0+228.00 - Sta. 0+355.00, Butuan City, Agusan del Norte | ME 3 CONST | 100.00% | DPWH |
| 22N00141 | Construction of Flood Mitigation Structure, Agusan River Basin (Bit-os Section), Sta. 0+124.935 - Sta. 0+244.00, Butuan City, Agusan del Norte | ME 3 CONST / HAPPY ALL3 BUILDERS CORP | 100.00% | DPWH |
| 23ND0064 | Construction of Flood Mitigation Structure, Barangay Marcos Calo, Las Nieves, Agusan del Norte | OLIN DEVELOPMENT ENGINEERING & CONST | 99.83% | DPWH |
| 24ND0092 | Construction of Flood Mitigation, Brgy. Anticala, Butuan City, Agusan del Norte | HAPPY ALL3 BUILDERS CORP | 99.74% | DPWH |
| 25ND0048 | Construction of Bank Protection, Lower Agusan River, Barangay Golden Ribbon, Butuan City | RAMISES CONST | 99.69% | DPWH |
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Completion schedule is shown for project and contractor flags only.
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Implementing office awards near-ABC contracts far more often than the flood-control baseline
{
"office": "Butuan City District Engineering Office",
"nearAbc": 48,
"trigger": "office_pattern_aggregate",
"officeId": "31ba81de-d2d4-5e62-9d89-1a64c3aa99c8",
"threshold": 0.995,
"binomialTailP": 4.827563674612978e-8,
"nearAbcRatePct": 100,
"totalContracts": 48,
"baselineRatePct": 70.4,
"excessPctPoints": 29.6,
"expectedNearAbc": 33.8,
"baselineDefinition": "share of all Sumbong flood-control contracts awarded at ≥99.5% of ABC"
}Source documents
Possible Innocent Explanations
- This may be due to highly competitive bidding where contractors consistently bid close to the ABC.