Construction of Flood Mitigation Structure24N00130

Construction of Flood Control Structure - Lower Agusan Development Project, Flood Control (Bancasi Bridge Revetment Upstream and Downstream), Package 2, Butuan City, Agusan del Norte

Construction of Flood Control Structure - Lower Agusan Development Project, Flood Control (Bancasi Bridge Revetment Upstream and Downstream), Package 2, Butuan City, Agusan del Norte is a DPWH-tracked public work in BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII. Reported contract value: ₱192,999,989.20. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to sumbong.

BUTUAN CITY (CAPITAL) (AGUSAN DEL NORTE), AGUSAN DEL NORTE, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation, Brgy. Anticala, Butuan City, Agusan del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0016636

₱39,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0018699

₱1,546,190.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0007396

₱1,397,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0008038

₱213,081.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0007398

₱129,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0006385

₱46,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-24-0013158

₱6,759,127.00 · FY2024

Released to Division of Northern Samar (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

357 projects · ₱29.2B total · 4 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱192,999,989.20

Progress

Reported complete (DPWH)

Start Date

April 10, 2024

Target End

May 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.