Schedule / Date Inconsistencies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23PM0018 (₱62.73M) is recorded as completed in 68 days against 205 planned; similar-cost projects take a median of 285 days, putting it in the fastest 1.4%. The project may have been completed quickly due to efficient work or overestimated original schedule.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Duli Flood Control, Sta. 123 + 580 - Sta. 123 + 680 (R.S.), Sta. 123 + 800 - Sta. 124 + 350 (R.S.), Bunot, Paracelis, Mountain Province23PM0018Flood control | 100% | December 30, 2023 | August 15, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: June 8, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-06-08T00:00:00.000Z",
"contractId": "23PM0018",
"actualEndDate": "2023-08-15T00:00:00.000Z",
"targetEndDate": "2023-12-29T00:00:00.000Z",
"contractCostPhp": 62725000
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo
Cite this record
Love the Philippines. “Schedule / Date Inconsistencies (C4): Construction of Duli Flood Control, Sta. 123 + 580 - Sta. 123 + 680 (R.S.), Sta. 123 + 800 - Sta. 124 + 350 (R.S.), Bunot, Paracelis, Mountain Province.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/47f820e8-9766-4c8c-bdd8-8876d54c6e0b
The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.