Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Awards Very Close to the Budget Ceiling

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23AA0147 was awarded at 100.00% of its ABC. Across its 22 recorded contracts, BJMJB CONST & SUPPLY was awarded at ≥99.5% of ABC 21 times (95.5%), versus 70.4% for flood-control contracts overall. This may be due to precise cost estimation or a highly competitive bidding process.

Public record entityConstruction of Flood Control Structure along Bislak River, Barangay Casilian to Barangay Cabaruan, Bacarra, Ilocos Norte
LocationBACARRA (ILOCOS NORTE), ILOCOS NORTE, Region IContract 23AA0147
Amount₱48,999,509.81100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structure along Bislak River, Barangay Casilian to Barangay Cabaruan, Bacarra, Ilocos Norte23AA0147Flood control100%December 28, 2023November 13, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: March 29, 2023 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Ilocos Norte 1st District Engineering Office",
  "ratio": 0.9999990583588135,
  "abcPhp": 48999555.95,
  "threshold": 0.995,
  "contractId": "23AA0147",
  "contractor": "BJMJB CONST & SUPPLY",
  "contractCostPhp": 48999509.81
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate
  • This may be due to precise cost estimation or a highly competitive bidding process.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)Ilocos NorteBacarraCasilian
Storms whose wind field reached it
Peilou 2026Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025
Hazard exposure
Active fault11.0 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)highUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgeinundated from SSA2 (3.01-4 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.