Love the Philippines

Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Bid-Ceiling Hugging

Contract cost is at or above 99.5% of ABC from Sumbong.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24BI0061 was awarded at 100.00% of its ABC. Across its 28 recorded contracts, V B MANUBAY CONST was awarded at ≥99.5% of ABC 28 times (100.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids at the maximum allowed amount to maximize revenue while staying within legal limits.

Public record entityConstruction of Sta. Lucia Flood Control Structure along Lamut River, Barangay Sta. Lucia, Bagabag, Nueva Vizcaya
LocationBAGABAG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region IIContract 24BI0061
Amount₱96,500,000.00100.00% of approved budget (ABC) sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Sta. Lucia Flood Control Structure along Lamut River, Barangay Sta. Lucia, Bagabag, Nueva Vizcaya24BI0061Flood control100%February 26, 2025September 1, 2024—completedsumbong source

Start: April 2, 2024 · Source fetched October 21, 2026

Rule Definition

ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.

Triggering Data & citations

Contract cost is at or above 99.5% of approved budget for contract (ABC)

{
  "deo": "Nueva Vizcaya District Engineering Office",
  "ratio": 1,
  "abcPhp": 96500000,
  "threshold": 0.995,
  "contractId": "24BI0061",
  "contractor": "V B MANUBAY CONST",
  "contractCostPhp": 96500000
}

Possible Innocent Explanations

  • Accurate cost estimating
  • Single qualified bid at market rate
  • ABC set equal to engineer’s estimate