Bid-Ceiling Hugging
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 24BI0061 was awarded at 100.00% of its ABC. Across its 28 recorded contracts, V B MANUBAY CONST was awarded at ≥99.5% of ABC 28 times (100.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids at the maximum allowed amount to maximize revenue while staying within legal limits.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Sta. Lucia Flood Control Structure along Lamut River, Barangay Sta. Lucia, Bagabag, Nueva Vizcaya24BI0061Flood control | 100% | February 26, 2025 | September 1, 2024 | — | completedsumbong source |
Start: April 2, 2024 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Nueva Vizcaya District Engineering Office",
"ratio": 1,
"abcPhp": 96500000,
"threshold": 0.995,
"contractId": "24BI0061",
"contractor": "V B MANUBAY CONST",
"contractCostPhp": 96500000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
