Awards Very Close to the Budget Ceiling
Contract cost is at or above 99.5% of ABC from Sumbong.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 22HL0077 was awarded at 100.00% of its ABC. Across its 19 recorded contracts, PHILSOUTH BUILDERS INC FORMERLY:PHILSOUTH BUILDERS was awarded at ≥99.5% of ABC 19 times (100.0%), versus 70.4% for flood-control contracts overall. It is possible that the contractor consistently bids at the maximum allowed amount to maximize revenue within legal limits.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Omanod River Control Structure, Sta. Catalina, Negros Oriental22HL0077Flood control | 100% | March 8, 2023 | March 8, 2023 | — | completedsumbong source |
Start: April 7, 2022 · Source fetched October 21, 2026
Rule Definition
ContractCost / ABC ≥ 0.995 using metadata.abc and contract cost fields.
Triggering Data & citations
Contract cost is at or above 99.5% of approved budget for contract (ABC)
{
"deo": "Negros Oriental 3rd District Engineering Office",
"ratio": 1,
"abcPhp": 49000000,
"threshold": 0.995,
"contractId": "22HL0077",
"contractor": "PHILSOUTH BUILDERS INC FORMERLY:PHILSOUTH BUILDERS",
"contractCostPhp": 49000000
}Source documents
Possible Innocent Explanations
- Accurate cost estimating
- Single qualified bid at market rate
- ABC set equal to engineer’s estimate
