Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: VEN RAY CONST CORP holds 39 flood-control contracts worth ₱2.25B, 2.22× the 95th-percentile contractor total (₱1.01B); up to 20 ran at the same time. This is a capacity question worth examining. Large contractors may have the resources and experience to handle many projects at once.

Public record entityVEN RAY CONST CORPOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 39Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control along Mangiskis River Downstream, Gingoog City, Misamis Oriental23KK0082Flood control100%March 5, 2024February 28, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Alubijid River Downstream of Alubijid Bridge (Left Side), Package 2, Alubijid, Misamis Oriental22K00281Flood control100%October 14, 2023October 14, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Alubijid River Downstream of Alubijid Bridge (Right Side), Package 1, Alubijid, Misamis Oriental22K00280Flood control100%May 20, 2024March 25, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Balatukan River, Package 2, Balingasag, Misamis Oriental24KK0056Flood control100%December 1, 2024December 1, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along CDO City Dominorog Camp Kibaritan Rd (Upstream and Downstream of Tal-uban Bridge) Phase 3, Talakag, Bukidnon22KC0037Flood control100%March 2, 2023March 2, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along CDO City Dominorog Camp Kibaritan Rd (Upstream and Downstream of Tal-uban Bridge), Phase 2, Talakag, Bukidnon22KC0044Flood control100%June 12, 2023June 12, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Show 33 more projects in this bucket
Construction of Flood Control Structure along Iponan River (Phase 2), Brgy. Iponan, Cagayan de Oro City, Misamis Oriental21K00275Flood control100%March 31, 2023March 31, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon24KA0131Flood control100%December 13, 2024December 13, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Downstream) of Dominorog Bridge, Talakag, Bukidnon24KC0018Flood control100%January 21, 2025January 20, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon23KC0017Flood control100%June 23, 2023June 22, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon24KC0030Flood control100%December 17, 2024December 13, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Cagayan de Oro City-Dominorog-Camp Kibaritan Rd, (Upstream and Downstream) of Pigcutin Bridge, Talakag, Bukidnon24KC0021Flood control100%May 26, 2025May 23, 2025No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Iponan River (Iponan Section), Iponan, Cagayan de Oro City, Sta. 1+885.10 - Sta. 2+183.8021K00274Flood control100%December 31, 2023March 25, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along lponan River, (Canito-An Section), Cagayan de Oro City22KH0030Flood control100%May 30, 2023May 30, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure along Sapangdaku River, Toledo City, Cebu24HF0045Flood control100%November 17, 2024November 15, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Barangay Alegria, Sta. 5+587 - Sta. 6+240, Tuburan, Cebu22HF0054Flood control100%June 13, 2023November 3, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Barangay Bakyawan, Sta. 0+000 - Sta. 0+412, Tuburan, Cebu22HF0038Flood control100%March 3, 2023March 3, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Caridad River, Barangay Caridad - Barangay Jagbuaya, Tuburan, Cebu23HF0031Flood control100%August 30, 2023August 30, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia - Barangay Bago, Asturias, Cebu24HF0006Flood control100%November 20, 2024November 20, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia - Barangay Tubigan, Asturias, Cebu23HF0040Flood control100%November 28, 2023November 28, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Langoyon River, Barangay Alegria - Barangay Cogon, Tuburan, Cebu23HF0020Flood control100%August 29, 2023August 29, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Langoyon River, Barangay Mangga, Sta. 0+607 - Sta. 0+916, Tuburan, Cebu22HF0040Flood control100%December 26, 2022January 24, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Langoyon River, Section 1: Sta. 0+362 - Sta. 0+602, Section 2: Sta. 2+320 - Sta. 2+520, Brgy. Mangga, Tuburan, Cebu22HF0050Flood control100%May 5, 2023June 23, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Mangoto River, Sta. 1+040 - Sta. 1+347, Brgy. Mangoto, Pinamungajan, Cebu22HF0051Flood control100%March 2, 2023March 2, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Sapangdaku River (Tributary Area), Barangay Juan Climaco Sr., Toledo City, Cebu24HF0005Flood control100%October 17, 2024October 17, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at Sapangdaku River, Barangay Daanglungsod - Barangay Dumlog, Toledo City, Cebu24HF0007Flood control100%September 5, 2024September 5, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Lamak Punod Sibago CIS Flood Protection Dike, Pinamungajan, Cebu24HF0046Flood control100%September 7, 2024September 6, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Shoreline Protection at Barangay Cabiangon along Toledo-Pinamungajan-Aloguinsan-Mantalongon Rd, Pinamungajan, Cebu23HF0010Flood control100%November 9, 2024November 9, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Shoreline Protection at Barangay Talavera along Toledo-Tabuelan-Sn Remigio Rd, Toledo City, Cebu23HF0002Flood control100%May 25, 2024May 24, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Mitigation Structure at Caridad River along Toledo-Tabuelan-Sn Remigio Rd, Barangay Jagbuaya, Tuburan, Cebu23HF0018Flood control100%September 6, 2023September 6, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia, Asturias, Cebu23HF0026Flood control100%October 26, 2023October 26, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia, Asturias, Cebu24HF0009Flood control100%July 14, 2024July 12, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Shoreline Protection, Barangay Daanlungsod, Tuburan, Cebu22HF0047100%March 12, 2024December 28, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Slope Protection Structure along Carcar-Barili Road, Sta. 56+000-Sta.57+000, Barili, Cebu22HF0035100%January 1, 2023December 28, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Slope Protection Structure at Langoyon River, Barangay Poblacion 8, Upstream, Sta. 2 + 520 - Sta. 2 + 721, Tuburan, Cebu22HF0095100%July 14, 2023September 1, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Bitan-Ag Creek (Upstream Section), Incl. Channelization, Package 18, Sta. 0+668.30 - Sta. 0+868.400, Cagayan de Oro City22K00260100%September 25, 2024March 25, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Control Structure, Bitan-Ag Creek, Package 12, Sta. 0+000.00 - Sta. 0+226.00, Downstream Section, Cagayan de Oro City22K00262100%September 2, 2024March 25, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Control Structure, Bitan-Ag Creek, Package 13, Sta. 0+226.00 - Sta. 0+456.70, Cagayan de Oro City22K00263100%September 25, 2024March 25, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Revetment for Tal-Uban Bridge (Downstream) along Cagayan de Oro City - Dominorog - Camp Kibaritan Road, Basak, Talakag, Bukidnon, K1485+460 (B01400MN)23KC0129100%November 28, 2023November 27, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "VEN RAY CONST CORP",
  "projectCount": 39,
  "totalValuePhp": 2248326622.9299994,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name

Connected records

Where this contractor works

Contractor grade B5 storms reached its projects · typhoon modeAll contractors & gradesContractor patterns