| Construction of Flood Control Structure along Iponan River (Phase 2), Brgy. Iponan, Cagayan de Oro City, Misamis Oriental21K00275Flood control | 100% | March 31, 2023 | March 31, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon24KA0131Flood control | 100% | December 13, 2024 | December 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Downstream) of Dominorog Bridge, Talakag, Bukidnon24KC0018Flood control | 100% | January 21, 2025 | January 20, 2025 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon23KC0017Flood control | 100% | June 23, 2023 | June 22, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Barandias-Dominorog Rd (Upstream) of Dominorog Bridge, Talakag, Bukidnon24KC0030Flood control | 100% | December 17, 2024 | December 13, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Cagayan de Oro City-Dominorog-Camp Kibaritan Rd, (Upstream and Downstream) of Pigcutin Bridge, Talakag, Bukidnon24KC0021Flood control | 100% | May 26, 2025 | May 23, 2025 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Iponan River (Iponan Section), Iponan, Cagayan de Oro City, Sta. 1+885.10 - Sta. 2+183.8021K00274Flood control | 100% | December 31, 2023 | March 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along lponan River, (Canito-An Section), Cagayan de Oro City22KH0030Flood control | 100% | May 30, 2023 | May 30, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure along Sapangdaku River, Toledo City, Cebu24HF0045Flood control | 100% | November 17, 2024 | November 15, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Barangay Alegria, Sta. 5+587 - Sta. 6+240, Tuburan, Cebu22HF0054Flood control | 100% | June 13, 2023 | November 3, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Barangay Bakyawan, Sta. 0+000 - Sta. 0+412, Tuburan, Cebu22HF0038Flood control | 100% | March 3, 2023 | March 3, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Caridad River, Barangay Caridad - Barangay Jagbuaya, Tuburan, Cebu23HF0031Flood control | 100% | August 30, 2023 | August 30, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia - Barangay Bago, Asturias, Cebu24HF0006Flood control | 100% | November 20, 2024 | November 20, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia - Barangay Tubigan, Asturias, Cebu23HF0040Flood control | 100% | November 28, 2023 | November 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Langoyon River, Barangay Alegria - Barangay Cogon, Tuburan, Cebu23HF0020Flood control | 100% | August 29, 2023 | August 29, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Langoyon River, Barangay Mangga, Sta. 0+607 - Sta. 0+916, Tuburan, Cebu22HF0040Flood control | 100% | December 26, 2022 | January 24, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Langoyon River, Section 1: Sta. 0+362 - Sta. 0+602, Section 2: Sta. 2+320 - Sta. 2+520, Brgy. Mangga, Tuburan, Cebu22HF0050Flood control | 100% | May 5, 2023 | June 23, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Mangoto River, Sta. 1+040 - Sta. 1+347, Brgy. Mangoto, Pinamungajan, Cebu22HF0051Flood control | 100% | March 2, 2023 | March 2, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Sapangdaku River (Tributary Area), Barangay Juan Climaco Sr., Toledo City, Cebu24HF0005Flood control | 100% | October 17, 2024 | October 17, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Flood Mitigation Structure at Sapangdaku River, Barangay Daanglungsod - Barangay Dumlog, Toledo City, Cebu24HF0007Flood control | 100% | September 5, 2024 | September 5, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Lamak Punod Sibago CIS Flood Protection Dike, Pinamungajan, Cebu24HF0046Flood control | 100% | September 7, 2024 | September 6, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Shoreline Protection at Barangay Cabiangon along Toledo-Pinamungajan-Aloguinsan-Mantalongon Rd, Pinamungajan, Cebu23HF0010Flood control | 100% | November 9, 2024 | November 9, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Shoreline Protection at Barangay Talavera along Toledo-Tabuelan-Sn Remigio Rd, Toledo City, Cebu23HF0002Flood control | 100% | May 25, 2024 | May 24, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure at Caridad River along Toledo-Tabuelan-Sn Remigio Rd, Barangay Jagbuaya, Tuburan, Cebu23HF0018Flood control | 100% | September 6, 2023 | September 6, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia, Asturias, Cebu23HF0026Flood control | 100% | October 26, 2023 | October 26, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Mitigation Structure at Guinabasan River, Barangay Sta. Lucia, Asturias, Cebu24HF0009Flood control | 100% | July 14, 2024 | July 12, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Shoreline Protection, Barangay Daanlungsod, Tuburan, Cebu22HF0047 | 100% | March 12, 2024 | December 28, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Slope Protection Structure along Carcar-Barili Road, Sta. 56+000-Sta.57+000, Barili, Cebu22HF0035 | 100% | January 1, 2023 | December 28, 2022 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Construction of Slope Protection Structure at Langoyon River, Barangay Poblacion 8, Upstream, Sta. 2 + 520 - Sta. 2 + 721, Tuburan, Cebu22HF0095 | 100% | July 14, 2023 | September 1, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Bitan-Ag Creek (Upstream Section), Incl. Channelization, Package 18, Sta. 0+668.30 - Sta. 0+868.400, Cagayan de Oro City22K00260 | 100% | September 25, 2024 | March 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Control Structure, Bitan-Ag Creek, Package 12, Sta. 0+000.00 - Sta. 0+226.00, Downstream Section, Cagayan de Oro City22K00262 | 100% | September 2, 2024 | March 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Flood Control Structure, Bitan-Ag Creek, Package 13, Sta. 0+226.00 - Sta. 0+456.70, Cagayan de Oro City22K00263 | 100% | September 25, 2024 | March 25, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
| Rehabilitation of Revetment for Tal-Uban Bridge (Downstream) along Cagayan de Oro City - Dominorog - Camp Kibaritan Road, Basak, Talakag, Bukidnon, K1485+460 (B01400MN)23KC0129 | 100% | November 28, 2023 | November 27, 2023 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |