Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: ST TIMOTHY CONST CORP holds 83 flood-control contracts worth ₱5.47B, 5.4× the 95th-percentile contractor total (₱1.01B); up to 64 ran at the same time. This is a capacity question worth examining. The contractor may have exceptional capacity or specialization in flood-control projects, allowing them to handle a large volume of contracts.

Public record entityST TIMOTHY CONST CORPOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 40Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Additional Booster Pump along Estero de Calubcob including Accessories, Manila City22OE0021Flood control100%February 24, 2023February 10, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Box Culvert along Tramo Road, Barangay Sta. Lucia, Pasig City23OB0066Flood control100%March 21, 2024June 3, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Canan Flood Control, La Paz, Abra22PA0077Flood control100%February 19, 2023January 31, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Cardona - Isit Flood Control, Barangay Cardona, Dolores, Abra22PA0049Flood control100%October 20, 2022October 20, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Duldulao Flood Control Structure, Barangay Duldulao, Malibcong, Abra22PA0050Flood control100%October 22, 2022October 27, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure (Naujan Seawall), Baragay Estrella Section, Naujan, Oriental Mindoro24E00038Flood control100%February 24, 2025August 15, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Show 34 more projects in this bucket
Construction of Flood Control Structure along Bongo River, Left Bank, Laoag River Basin Flood Control and Sabo Project, Brgy. Caray, Sitio Bangbangcag, Nueva Era, Ilocos Norte22A00262Flood control100%October 28, 2022October 28, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure along Bongo River, Right Bank, Laoag River Basin Flood Control and Sabo Project, Brgy. Caray, Sitio Bangbangcag, Nueva Era, Ilocos Norte22A00263Flood control100%October 28, 2022October 28, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure Along Puray River, Rodriguez, Rizal23DO0055Flood control100%February 1, 2024September 25, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structure, Sitio Binayoyo (Downstream) Phase II, Brgy. Calawis, Antipolo City22DN0029Flood control100%October 27, 2022October 27, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structures of Lukutang Malaki River (Tributary of Marikina River), Phase III, Sitio Anginan, Brgy. San Isidro, Rodriguez, Rizal22DO0048Flood control100%December 13, 2022August 22, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structures of Lukutang Malaki River (Tributary of Marikina River), Phase IV, Sitio Anginan, Brgy. San Isidro, Rodriguez, Rizal22DO0051Flood control100%December 21, 2022August 22, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Control Structures of Lukutang Malaki River (Tributary of Marikina River), Phase V, Sitio Anginan, Brgy. San Isidro, Rodriguez, Rizal22DO0052Flood control100%December 21, 2022October 3, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure (Installation of Booster Pump) and Groundsill at Villanueva Creek Near Salvador Bridge, District 1, Parañaque City23OC0038Flood control100%April 9, 2024April 9, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structure at East Manggahan River, Brgy. San Juan, Taytay, Rizal22D00057Flood control100%November 30, 2023November 30, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Flood Mitigation Structures (Installation of Booster Pump) and Groundsill at Marulas Creek, District 1, Parañaque City22OC0054Flood control100%May 13, 2023May 13, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Grouted Riprap Slope Protection Wall along Bulubok Creek from Rural Bank of Montalban to Sitio Adia, Rodriguez, Rizal21DO0067Flood control100%August 18, 2022August 18, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Gucab - Demet Flood Control, La Paz, Abra21PA0220Flood control100%July 21, 2022July 12, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Gucab Flood Control, Barangay Poblacion, La Paz, Abra22PA0093Flood control100%December 8, 2022December 8, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Patagui Flood Control, Poblacion, La Paz, Abra22PA0085Flood control100%December 8, 2022December 8, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Poblacion Flood Control Structure (Phase 2), Barangay Poblacion, La Paz, Abra22PA0088Flood control100%October 9, 2022October 9, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Poblacion Flood Control Structure (Phase 3), Barangay Poblacion, La Paz, Abra22PA0089Flood control100%October 11, 2022November 10, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Ransang River Flood Control Structure, Rizal, Palawan24EF0047Flood control100%September 15, 2024October 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Retention Basin along Estero de Valencia Phase III, Manila City21OE0018Flood control100%November 30, 2022November 30, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Riverwall along Malabon-Tullahan River (Phase 4), Brgy. Potrero, Malabon City22OA0034Flood control100%February 8, 2023February 8, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Road Dike along Bucayao River (East Side), Sitio Malaya Section, Barangay Tagumpay, Naujan, Oriental Mindoro24E00052Flood control100%February 24, 2025July 4, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Sabangan Flood Control, Buli, La Paz, Abra22PA0084Flood control100%October 9, 2022October 19, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Sagang Flood Control, Lacub, Abra21PA0235Flood control100%July 24, 2022July 24, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Salip Flood Control, Barangay Poblacion, La Paz, Abra22PA0079Flood control100%September 27, 2022September 27, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Soot Flood Control Structure (Phase 2), Barangay Mudeng, La Paz, Abra22PA0090Flood control100%October 11, 2022October 11, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Sto. Tomas Flood Control, Manabo, Abra22PA0048Flood control100%August 22, 2022August 23, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation of Flood Mitigation Structure, Buli Creek at Barangay San Miguel and Pinagbuhatan, Pasig City23OB0090Flood control100%September 3, 2023September 3, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Drainage System (Box Culvert) along Labores Street, Pandacan, Manila22OH0081100%January 8, 2024December 22, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Lined Canal, Barangay Sto Tomas, Biñan, Laguna21DI0029100%July 13, 2022July 13, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Revetment along Cabuyao River, Cabuyao City, Laguna22DI0011100%September 29, 2022August 20, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Revetment along Malaking Ilog River (Phase 3), Barangay Lipahan, San Juan, Batangas22DD0067100%October 31, 2022October 31, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Slope Protection Along Taguig River, Facing Downstream (East Bank), Package 5, Taguig City22OB0106100%March 6, 2023January 11, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Slope Protection Along Taguig River, Facing Downstream (West Bank), Package 4, Taguig City22OB0105100%October 13, 2022October 13, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Slope Protection Along Taguig River, Facing Downstream (West Bank), Package 5, Taguig City22OB0108100%November 18, 2022November 18, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Rehabilitation/Slope Protection of Sitio Paenaan River, along Marikina-Infanta Road (Upstream Phase 5), Brgy. San Jose, Antipolo City22DN0030100%March 12, 2023March 12, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "ST TIMOTHY CONST CORP",
  "projectCount": 83,
  "totalValuePhp": 5473908419.179998,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name

Connected records

Where this contractor works

Contractor grade F35 storms reached its projects · typhoon modeAll contractors & gradesContractor patterns