Contractor Concentration (Flood Control)
A contractor holds a very large share of flood-control contract value in a district or province.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: J G ORANZA CONST received 41.9% (₱825.86M of ₱1.97B) of recorded flood-control contract value in South Cotabato 1st District Engineering Office across 28 contracts and 12 contractors, above the 40% concentration threshold (HHI 0.206). This may be due to the contractor's strong track record or capacity in the area.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
Flagged peer group: South Cotabato 1st District Engineering Office
Show 5 more projects in this bucket
| Construction of Concrete Revetment, P.I. Silway River, Barangay Apopong, General Santos City21MB0023 | 100% | October 12, 2022 | September 20, 2022 | — | completedsumbong source |
| Construction of Flood Control/Concrete Revetment along Tinagacan-Buayan River (Phase 2), Barangay Tinagacan, General Santos City21MB0022 | 100% | March 21, 2023 | March 21, 2023 | — | completedsumbong source |
| Construction of Revetment along Makar River, General Santos City22MB0022 | 100% | September 10, 2022 | September 10, 2022 | — | completedsumbong source |
| Construction of Revetment along Tinagacan-Buayan River (Phase 3), Brgy. Tinagacan, General Santos City22MB0024 | 100% | December 23, 2022 | January 20, 2023 | — | completedsumbong source |
| Construction of River Bank Protection, Lusanes, Brgy. Sulit, Polomolok, South Cotabato24M00219 | 100% | April 15, 2025 | February 4, 2025 | — | completedsumbong source |
Rule Definition
Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.
Triggering Data & citations
Contractor share of flood-control contract value in peer group exceeds typical concentration
{
"hhi": 0.20618652345561594,
"scope": "deo",
"bucketKey": "deo:South Cotabato 1st District Engineering Office",
"contractor": "J G ORANZA CONST",
"thresholds": {
"hhi": 0.25,
"share": 0.4
},
"bucketTotalPhp": 1969054604.06,
"contractorShare": 0.4194207242588153,
"contractorTotalPhp": 825862308.14
}Source documents
Possible Innocent Explanations
- Dominant local contractor with equipment already in the area
- Emergency or accelerated procurement after a disaster
- Small number of qualified flood-control firms in the province
- This may be due to the contractor's strong track record or capacity in the area.