Construction of Revetment21MB0022

Construction of Flood Control/Concrete Revetment along Tinagacan-Buayan River (Phase 2), Barangay Tinagacan, General Santos City

Construction of Flood Control/Concrete Revetment along Tinagacan-Buayan River (Phase 2), Barangay Tinagacan, General Santos City is a DPWH-tracked public work in SOUTH COTABATO, Region XII. Reported contract value: ₱45,389,626.18. Status: Reported complete (DPWH). Contractor on record: J G ORANZA CONST. Figures trace to sumbong.

SOUTH COTABATO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Concrete Revetment along Tinagacan-Buayan River (Phase 2), Barangay Tinagacan, General Santos City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007615

₱61,700,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010325

₱45,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010322

₱4,700,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱45,389,626.18

Progress

Reported complete (DPWH)

Start Date

March 11, 2022

Target End

March 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.